Corscale: Project Gravity

Site planned for 2029 and has expansions through 2030
Utility Provider: PPL Electric Utilities
Floors: 2
Lot Size: 186 acres

Project Gravity is a planned seven-building data center campus on a 186-acre former mining site in Archbald, Lackawanna County, near the Jermyn border. Archbald 25 Developer LLC, linked to Western Hospitality Partners, filed the plans in 2025 and won conditional preliminary approval under the borough's 2023 zoning in September 2025. Corscale bought the land in December 2025 through US Gravity Purchaser LLC, with Affinius Capital. The plan includes an on-site substation and a large battery energy storage system that reduces the number of diesel generators. Corscale says it has a hyperscale tenant. Final land development plans were filed in September 2026.

Site History

  • September 2026: Corscale files final land development plans.
  • December 2025: Corscale buys the site.
  • September 2025: The borough grants conditional preliminary approval.
  • April 2025: Archbald 25 Developer files plans.

Map and Nearby Locations

Scranton Carbondale Hwy
Corscale Sites
Nearby Facilities

Corscale: Project Gravity Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Corscale: Project Gravity

Distance Site About
0.41 miles Provident: Project North
Provident's Project North is a smaller data center campus proposed on about 66 acres at the Archbald-Jermyn border; its plan has stalled.
0.55 miles Provident: Project Scott Expansion
Later phases of Provident's Project Scott data center campus in Archbald, Lackawanna County.
0.75 miles PDC Realty: Project Boson
Project Boson is a proposed single-building data center on the former Highway Auto Parts salvage yard in Archbald, Lackawanna County.
0.81 miles Provident: Project Scott
Provident Realty Advisors' Project Scott is an 18-building data center campus proposed north of Ed Staback Memorial Park in Archbald, Lackawanna County.
1.93 miles Cornell Realty: Wildcat Ridge Expansion
Later phases of Cornell Realty Management's proposed Wildcat Ridge data center campus in Archbald, Lackawanna County.
2.10 miles Cornell Realty: Wildcat Ridge AI DC Campus
Cornell Realty Management's proposed 14-building Wildcat Ridge data center campus in Archbald, Lackawanna County, denied by borough council in October 2026.
2.17 miles Project Green Mountain (Archbald)
A proposed seven-building data center campus on the former Stavola quarry along Salem Road in Archbald, Lackawanna County.
2.99 miles Real Estate Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
3.38 miles Catalyst: Breaker Street Data Center
A proposed six-building data center campus on Breaker Street in Jessup, Lackawanna County, denied by the zoning hearing board in January 2026.
3.66 miles PNK Group: Valley View (Archbald)
PNK Group plans two data centers in the Archbald section of the Valley View Business Park, Lackawanna County.
3.76 miles DBT Data: Lackawanna One
DBT-Data proposes a single-story data center on the former TMG Health site in the Valley View Business Park, Jessup, Lackawanna County.
3.82 miles Catalyst: Sunnyside Road Data Center
Catalyst Commercial Development's planned data center on Sunnyside Road in Jessup, Lackawanna County, on a site first approved for a warehouse.
9.05 miles Scranton Materials: Ransom Township Quarry
A proposed six-building data center campus at the Scranton Materials quarry in Ransom Township, Lackawanna County, denied an overlay in January 2026.
9.17 miles Popca LLC: Scranton Bldg2
The second building of Popca LLC's proposed data center campus in Newton Township, Lackawanna County.
9.27 miles Popca LLC: Scranton Bldg1
Popca LLC's proposed two-building data center campus in Newton Township, Lackawanna County, denied by the zoning officer in 2026 and under appeal.
10.17 miles Linde: Clinton Township Data Center Campus
Linde Corporation's proposed data center and power campus in Clinton Township, Wayne County, rejected by township supervisors in September 2026 and under appeal.
13.37 miles Mudiita Infra: Ransom Township, PA
A stalled data center plan on land in Ransom Township, Lackawanna County, that Mudiita Land Venture bought in July 2026.
17.91 miles Gouldsboro Expansion
Later phases of the Gouldsboro (Project Gold) data center campus in Clifton and Covington townships, Lackawanna County.
19.07 miles Gouldsboro 1
A proposed 11-building data center and gas power campus on about 1,000 acres along Interstate 380 in Clifton and Covington townships, Lackawanna County.

Corscale: Project Gravity Data Center Photos See all

Proposed Site for Project Gravity in Archbald, Pennsylvania
Source: Google Maps

Operating Company

Operated by:

Corscale is the data center platform of Patrinely Group, a Houston real estate developer, built with its investment partner Affinius Capital (formerly USAA Real Estate). It designs, builds and operates large, energy-efficient campuses for hyperscale customers in Tier 1 and select Tier 2 markets.

Its first campus, Gainesville Crossing in Prince William County, Virginia, covers 130 acres near Interstate 66 and is planned for five two-story buildings totaling about 2.3 million square feet. Corscale is also developing Midwest Digital Gateway, a four-building campus in Canton, Ohio, and a campus at Court Lane in Iver, west of London.

Corscale History:

  • In September 2026, Corscale's project company bought the 162-acre Midwest Digital Gateway site in Canton, Ohio.
  • In June 2026, the Corscale and Affinius joint venture closed a $975 million refinancing from Blue Owl Capital for a fully leased building at Gainesville Crossing.
  • In May 2024, Corscale delivered its first building at Gainesville Crossing.
  • In February 2022, Corscale broke ground on Gainesville Crossing.
  • In late 2021, Patrinely Group launched Corscale and named Gainesville Crossing as its first campus.
0
Facilities
0
Markets

News See all

Read CorScale Plans 140MW Data Center Campus Outside London for 2029 Start
CorScale is set to advance its first UK project. The company has appointed McLaren Construction and Phoenix ME to begin predevelopment work on a data center in Iver, Buckinghamshire. The 14-acre Co...

CorScale Plans 140MW Data Center Campus Outside London for 2029 Start

June 06, 2026 Corscale

CorScale is set to advance its first UK project. The company has appointed McLaren Construction and Phoenix ME to begin predevelopment work on a data center in Iver, Buckinghamshire. The 14-acre Court Lane site could deliver up to 140MW across two multi-story buildings, with plans dating back to...

Read more
Read CorScale Plans to File FOr Permission To Develop a 140MW Facility in Iver, Buckinhamshire
CorScale Plans to File FOr Permission To Develop a 140MW Facility in Iver, Buckinhamshire

CorScale Plans to File FOr Permission To Develop a 140MW Facility in Iver, Buckinhamshire

November 30, 2022 Corscale

New data center company CorScale is looking to develop its first international data center in the UK. According to the Senior Vice President of CorScale, the company is a few days away from filing for planning permission to develop the facility in Iver, outside London. CorScale noted that the...

Read more
Read Corscale launches data center platform with Northern Virginia Campus
Corscale launches data center platform with Northern Virginia Campus

Corscale launches data center platform with Northern Virginia Campus

February 24, 2022 Corscale

Corscale, a new data center development platform, has announced that it has broken ground on its first data center campus in Northern Virginia. The brainchild of real estate firm Patrinely Group and its capital partner, USAA Real Estate, Corscale, will launch the first phase of its project, a...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.