Bitdeer: Fox Creek, AB

Latest Podcast Opal Power Plant, SW-21-62-19-W5M
Under Construction
New facility under construction
Operated by:

Bitdeer: Fox Creek, AB

Year Planned: 2027
Utility Provider: ATCO Electric
Ownership: BitDeer owns the building.
Lot Size: 19 acres

Site History

  • 2022: The Alberta Utilities Commission approves the Opal gas-fired power plant for Kiwetinohk Energy.
  • February 2025: Bitdeer buys the fully permitted Opal site and power project from Kiwetinohk.
  • March 2025: The utilities commission transfers the power plant approval to Bitdeer.
  • June 2026: Bitdeer breaks ground on the campus.
  • August 2026: Bitdeer moves energization to Q4 2027.

Project Profile

  • Developer: Bitdeer Technologies Group
  • Land: about 19 acres on Crown land south of Fox Creek
  • Design: the data centre runs behind the fence on the on-site gas plant, with a grid connection to export power at peak demand
  • Cooling: closed-loop dry cooling, designed for bitcoin mining at first and for AI and HPC later
  • Status: Construction

Map and Nearby Locations

Opal Power Plant, SW-21-62-19-W5M
BitDeer Sites
Nearby Facilities

Bitdeer: Fox Creek, AB Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Operating Company

Operated by:

Bitdeer is a leading miner sharing service platform, where users are provided with a full range of cryptocurrency mining and cloud hosting solutions.

0
Facilities
0
Markets

News See all

Read FingerMotion, Genius Group Sign JV For 2.4MW HPC Campus In Alberta
Genius Group, [FingerMotion](https://baxtel.com/data-centers/fingermotion) and BlueFlare Energy Solutions signed [binding agreements](https://ir.geniusgroup.net/news-events/press-releases/detail/26...

FingerMotion, Genius Group Sign JV For 2.4MW HPC Campus In Alberta

October 28, 2026 FingerMotion

Genius Group, FingerMotion and BlueFlare Energy Solutions signed binding agreements on October 27 to form GENIUSpark Alberta Inc. and build high-performance computing campuses in Alberta, Canada. The first site, Hanna Campus No. 1, carries an estimated $24.3 million cost and 2.4 MW of computing...

Read more
Read Bitdeer AI Secures 65MW Data Center Lease In Johor, Malaysia
Bitdeer AI has signed a 10-year data center services agreement for the 65.1MW A202 facility in Johor Bahru, Malaysia. The liquid-cooled facility will host Nvidia GB300 and NVL72 systems and is Bitd...

Bitdeer AI Secures 65MW Data Center Lease In Johor, Malaysia

September 18, 2026 BitDeer

Bitdeer AI has signed a 10-year data center services agreement for the 65.1MW A202 facility in Johor Bahru, Malaysia. The liquid-cooled facility will host Nvidia GB300 and NVL72 systems and is Bitdeer’s largest single capacity addition in Southeast Asia. Located alongside the 21.7MW A201...

Read more
Read Bitdeer Acquires 200 Acres In Milam County, Texas, For AI And HPC Expansion
Bitdeer has acquired a 200-acre site in Milam County, Texas, for $100 million to support its AI and HPC infrastructure expansion. The land, formerly part of an Alcoa aluminum smelting plant, is adj...

Bitdeer Acquires 200 Acres In Milam County, Texas, For AI And HPC Expansion

September 05, 2026 BitDeer

Bitdeer has acquired a 200-acre site in Milam County, Texas, for $100 million to support its AI and HPC infrastructure expansion. The land, formerly part of an Alcoa aluminum smelting plant, is adjacent to Bitdeer’s existing Rockdale data center. The company said the combined sites provide 563MW...

Read more
Read Avax One Targets 10MW Behind-the-Meter Data Center in Alberta
Avax One Targets 10MW Behind-the-Meter Data Center in Alberta

Avax One Targets 10MW Behind-the-Meter Data Center in Alberta

April 11, 2026 Alberta

Cryptocurrency firm Avax One Technology has signed a front-end engineering and design (FEED) proposal for a 10MW off-grid, natural gas-powered AI and high-performance computing (HPC) data center at the 4-31 Battery site in Alberta, Canada. The FEED study will be led by BlueFlare Energy Solutions...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts

Ready to Level up Your
Data Center Strategy?