Balloonist: Red Cedar, WI

Latest Podcast N6778 County Rd B
In Doubt
The development is facing regulatory or community opposition
Operated by: Balloonist LLC

Balloonist: Red Cedar, WI

Utility Provider: Xcel Energy
Lot Size: 309 acres

Balloonist LLC owns about 310 acres north of Interstate 94 in Menomonie, between 650th and 690th Avenues. The city annexed the land from the Town of Red Cedar and rezoned it in August 2025 for a proposed $1.6 billion data center campus. Plans showed as many as 15 buildings and equipment yards.

The city council paused the project in September 2025 after public opposition. In January 2026 Menomonie created a data center zoning district, and Balloonist must reapply under it. The city delayed a vote on the zoning rules in October 2026. Balloonist has said construction would not start before 2027.

Site History

  • October 2026: The city council delays a vote on data center zoning rules.
  • January 2026: Menomonie creates a data center zoning district, so the project must reapply.
  • September 2025: The city council pauses the project.
  • August 2025: The city annexes and rezones the land from the Town of Red Cedar.

Map and Nearby Locations

N6778 County Rd B
Balloonist LLC Sites
Nearby Facilities

Sites within 15 miles of Balloonist: Red Cedar, WI

Distance Site About
18.92 miles AT&T: 304 S Dewey St, Eau Claire
AT&T's main telephone exchange in downtown Eau Claire, Wisconsin, the hub of the city's wireline network.

Balloonist: Red Cedar, WI Data Center Photos See all

Proposed sitemap for Balloonist LLC's data center in Red Cedar, Wisconsin
Source: City of Menomonie

Operating Company

Operated by: Balloonist LLC
0
Facilities
0
Markets

News See all

Read Data Center Development in Wisconsin delayed
Data Center Development in Wisconsin delayed

Data Center Development in Wisconsin delayed

September 26, 2025 Wisconsin

A data center development in Menomonie, Wisconsin, has been delayed. In a meeting on September 22, Mayor Randy Knaack said that he had drafted a memo to developer Balloonist LLC stating that the city was no longer interested in pursuing the project.“I’m not thrilled about the data center coming...

Read more
Read Northwestern Mutual Abandons Franklin, Wisconsin Facility And On-site Data Center
Northwestern Mutual Abandons Franklin, Wisconsin Facility And On-site Data Center

Northwestern Mutual Abandons Franklin, Wisconsin Facility And On-site Data Center

February 22, 2023 Wisconsin

Northwestern Mutual is abandoning its campus in Franklin, Wisconsin, on the outskirts of Milwaukee, as part of a $500 million effort to relocate to an office complex in downtown Milwaukee. Per the Milwaukee Journal Sentinel, this is partially due to the fact that the corporation no longer needs...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.