Amazon Data Services Italy is building Building A, the larger of two data centers on former industrial land beside the Rho Fiera exhibition center. The campus straddles Rho and Pero and takes in the former Vivaldi, CAM Petroli and IP oil depot sites. Building A is a single block about 176 m long and 20 m high, with twelve data halls. Two underground 132 kV cables from Terna's Bollate station will feed a new on-site substation. An orchard of about 3 hectares on the site is kept for biodiversity. Amazon plans to finish commissioning the building by the end of 2028.
Site History
-
2026-10: The ministry clears new wells and a water treatment building for the campus.
-
2026-01: Amazon files the start of works on Building A.
-
2025-12: Rho issues the building permit for Building A.
-
2025-09: The Ministry of Environment approves the campus environmental impact assessment, with conditions.
-
2024-11: The Council of Ministers declares AWS's Milan region investment of strategic national interest.
-
2024-04: Amazon buys the land from Vailog, SEGRO's Italian arm.