Amazon Web Services plans its PIT100 data center campus at the Homer City Energy Campus in Center and Black Lick Townships, Indiana County, on land it proposes to buy from Homer City Redevelopment. The plan calls for 39 two-story data center buildings of about 225,000 sq ft each, grouped in six phases named Rura, West, Harvey Gaston, Bruner, Green and Helen. Power will come from FirstEnergy, supported by the 4.5 GW natural gas plant that Homer City Redevelopment is building on the former Homer City Generating Station site. Cooling water will come from the plant's existing withdrawal rights, and AWS expects 1,500 to 2,000 jobs.
Indiana County accepted the preliminary land development plan for review in October 2026, with a decision due by January 2027. AWS plans to start construction once permits are approved, and the last phase is scheduled to finish in 2036.
Site History
-
October 2026: The Indiana County Planning Commission accepts the plan for review.
-
August 2026: AWS files its preliminary land development plan.
-
November 2025: The state DEP approves the air permit for the Homer City gas plant.