Ridge GammaInterested in this information?Contact us

Latest Podcast Street AddressInterested in this information?Contact us, Becker, MN 55308, United States
Withdrawn
Project cancelled before construction
Operated by:

Amazon: Becker, MN

Ownership: Amazon AWS owns the building.
Lot Size: 348 acres
  • Update: Amazon has suspended plans for this data center in Becker, Minnesota.

Site History

Amazon Data Services acquired 348 acres in Becker, Minnesota for $73.6 million to develop a data center project. The land was previously part of Xcel Energy Inc.'s Sherco Site. Amazon is proposing to install 250 diesel generators at its planned data center.

The transaction involved several ownership changes: Elk River Technologies first purchased the parcel from Xcel Energy in April 2024 for $7.97 million, then sold it to Amazon—representing a substantial price increase in a short period.

This development comes after earlier plans for the site fell through in 2022, when negotiations between Xcel Energy and Google for a potential data center project were unsuccessful.

In February 2024, Microsoft bought 300 acres of land from Xcel nearby in Becker.

Map and Nearby Locations

This Facility
Amazon AWS Sites
Nearby Facilities

Sites within 15 miles of Hub OneInterested in this information?Contact us

Distance Site About
NN milesInterested in this information?Contact us Tower AlphaInterested in this information?Contact us
Microsoft bought about 295 acres in the city of Becker for a future data center.
NN milesInterested in this information?Contact us Scannell Tech Expansion
NN milesInterested in this information?Contact us Scannell Technology Park
Real estate firm Scannell Properties is planning a new data center development in Monticello, tentatively called the Scannell Technology Park.
NN milesInterested in this information?Contact us Monticello Tech Park
The development could eventually total 3 million square feet (278,709 sqm) of space, spread across multiple buildings, each potentially around 300,000 square feet (27,871 sqm).
NN milesInterested in this information?Contact us Monticello Tech Expansion
NN milesInterested in this information?Contact us UnitedHealth Elk River
NN milesInterested in this information?Contact us Target Elk River
NN milesInterested in this information?Contact us Swervo: Elk River, MN
Elk River city officials in Minnesota have rejected a proposal by Swervo Development Corp. and Irongate Data Centers to convert a 60,000-square-foot warehouse into a data center.

Operating Company

Operated by:

Amazon Web Services (AWS) is a subsidiary of Amazon.com that provides on-demand cloud computing platforms to individuals, companies and governments, on a paid subscription basis.

0
Facilities
0
Markets

News See all

Read AWS Receives Planning Approval for Data Center in Iver, UK
Amazon Web Services (AWS) has received planning approval for a new data center project in Iver, Buckinghamshire, UK. Buckinghamshire Council approved the development, which will replace 17 industri...

AWS Receives Planning Approval for Data Center in Iver, UK

October 01, 2026 Amazon AWS

Amazon Web Services (AWS) has received planning approval for a new data center project in Iver, Buckinghamshire, UK. Buckinghamshire Council approved the development, which will replace 17 industrial and warehouse units with a data center featuring 27 backup generators. Planning officers...

Read more
Read Generac Secures $8bn Backup Generator Deal With Amazon
Generac has signed a long-term deal to supply backup generators to Amazon’s data centers. The agreement includes about $2.4 billion in deliveries over two years and could reach $8 billion overall. ...

Generac Secures $8bn Backup Generator Deal With Amazon

September 26, 2026 Amazon AWS

Generac has signed a long-term deal to supply backup generators to Amazon’s data centers. The agreement includes about $2.4 billion in deliveries over two years and could reach $8 billion overall. Amazon will also have the option to buy nearly 1.7 million Generac shares. “It provides visibility...

Read more
Read Prysmian, Rio Tinto To Supply Low-Carbon Aluminum For Amazon Data Center In Ohio
Italian cable manufacturer Prysmian and mining company Rio Tinto will supply an Amazon data center in Ohio with low-carbon aluminum electrical cables. The aluminum will be produced by Elysis, a joi...

Prysmian, Rio Tinto To Supply Low-Carbon Aluminum For Amazon Data Center In Ohio

September 21, 2026 Amazon AWS

Italian cable manufacturer Prysmian and mining company Rio Tinto will supply an Amazon data center in Ohio with low-carbon aluminum electrical cables. The aluminum will be produced by Elysis, a joint venture between Rio Tinto and Alcoa. Its smelting process uses proprietary inert anodes instead...

Read more
Read Qualcomm And AWS Collaborate On Custom AI Silicon For Large-Scale Data Centers
Qualcomm is partnering with Amazon to develop customized AI infrastructure solutions. Under the multi-generational partnership, Qualcomm Technologies and Amazon will develop custom silicon for larg...

Qualcomm And AWS Collaborate On Custom AI Silicon For Large-Scale Data Centers

September 08, 2026 Amazon AWS

Qualcomm is partnering with Amazon to develop customized AI infrastructure solutions. Under the multi-generational partnership, Qualcomm Technologies and Amazon will develop custom silicon for large-scale AI data centers, focusing on AI inference and optical connectivity of up to 1.6T. The...

Read more
Read Amazon Acquires 8,000-Acre Texas Site for Gas-Powered Data Center
Amazon has acquired an 8,000-acre site in Pecos, Texas, where it plans to develop a data center powered by an on-site natural gas plant that could become one of the largest in the US. According to ...

Amazon Acquires 8,000-Acre Texas Site for Gas-Powered Data Center

August 10, 2026 Amazon AWS

Amazon has acquired an 8,000-acre site in Pecos, Texas, where it plans to develop a data center powered by an on-site natural gas plant that could become one of the largest in the US. According to Cleanview reporting, Amazon acquired the GW Ranch site from Pacifico Energy for the planned...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts

Ready to Level up Your
Data Center Strategy?