PDG's MU1 data center campus is taking shape in the heart of Navi Mumbai's tech corridor. Set within a planned 50-acre IT park in Airoli, this state-of-the-art facility will feature five purpose-built data centers. The strategic location offers hyperscalers and enterprises two critical advantages: robust power infrastructure and seamless network connectivity, ensuring optimal performance for their mission-critical operations.
Launched in 2022 with a USD 300 million investment, the first data center building, DC1, has achieved the prestigious IGBC Platinum certification. MU1 is also India’s first OCPTM (Open Compute Project) ready facility.
https://princetondg.com/locations/mu1/
MU1 Campus features
- Highly reliable 220 kV substation with diverse feeds from two independent utility substations
- Distributed/N+N redundant UPS system
- N+2 Redundancy for transformer and generators
- Independent set of transformers and diesel generators for IT and mechanical load
- UPS with 10 mins battery backup EOL
- 48 hours of on site fuel back up
Certifications
- Mumbai's first IGBC (Indian Green Building Council)
- Platinum Certified Site
- First OCP (Open Compute Project) Ready Site in
- India Uptime Tier III Certified
- ISO 9001 , 20000, 27001, 45001, 22301
- PCI DSS