Project Tembo began as Project Jade, a campus Crusoe and Tallgrass Energy planned in the Switchgrass Industrial Park on US 85 south of Cheyenne, Laramie County. After Crusoe withdrew in 2026, Google took direct control through its affiliate Jupiter Star Holdings LLC. In July 2026, the county record cut the plan from five buildings to four, with peak construction staffing halved. Related Digital is a project partner.
Facilities. The four data halls sit on the park's northeast lots. The plan also includes office, logistics and network buildings and a battery storage system. Google's HUB-1 office support building stands on a separate tract east of the park along US 85.
Power. Black Hills Energy serves the campus under a large power contract that took effect in September 2026 and runs through 2048. Supply combines new Black Hills gas generation, Tallgrass's Cheyenne Power Hub on the park's southwest lots and an AEP fuel-cell installation, managed as a private microgrid with a limited grid connection.