Data Center Campus

Crusoe: Abilene AI Campus

11 sites West Texas
OperationalPlannedUnder ConstructionProspective Expansion
Fully operational facility with expansion in progress and future phases planned and prospective expansion planned
Operated by:

Campus at a Glance

11 data centers on this campus
First built in 2025 with expansions through 2028
Total building size: 1,996,000 SqFt

Operators on this campus:

  • Crusoe
  • OpenAI
Coordinates: 32.50504, -99.78104
░░░░░ Request Dataset MW
Operational
░░░░░░░ Request Dataset MW
Under Construction
░░░░░ Request Dataset MW
Planned

Tech partners Lancium and Crusoe Energy are building a next-gen data center at Lancium's Clean Campus. The first phase is a 998,000 square foot facility designed to handle huge AI workloads, supporting up to 100,000 GPUs per building.

Backed by a major investment, the project focuses on renewable energy and high-density computing. The first two-building is fully leased to a Fortune 100 tech company.

Lancium will power the future with smart energy solutions, while Crusoe builds the digital infrastructure that will drive AI's next frontier.

Buildings

Sites on this Campus

Site Operator Status Operational Building Size Built
Crusoe: Abilene 1 Crusoe
Operational
░░░░░ Request Dataset MW 499,000 SqFt 2025
Crusoe: Abilene 10 Crusoe
Planned
— — 2028
Crusoe: Abilene 2 Crusoe
Operational
░░░░░ Request Dataset MW 499,000 SqFt 2025
Crusoe: Abilene 3 Crusoe
Operational
░░░░░ Request Dataset MW — 2026
Crusoe: Abilene 4 Crusoe
Operational
░░░░░ Request Dataset MW — 2026
Crusoe: Abilene 5 Crusoe
Under Construction
— — 2027
Crusoe: Abilene 6 Crusoe
Under Construction
— — 2027
Crusoe: Abilene 7 Crusoe
Under Construction
— — 2027
Crusoe: Abilene 8 Crusoe
Under Construction
— — 2027
Crusoe: Abilene 9 Crusoe
Under Construction
— — 2027
PointInterested in this information?Contact us OpenAI
Under ConstructionOperationalProspective Expansion
░░░░░ Request Dataset MW 998,000 SqFt 2025

Map and Nearby Locations

Crusoe: Abilene AI Campus Power Growth Over Time

+130% since 2022
Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Operating Company

Operated by:

Crusoe is a privately held AI infrastructure developer and GPU cloud provider that builds AI data center campuses and offers GPU cloud services in the United States. The company began as Crusoe Energy Systems, a flare mitigation provider that powered onsite computing from stranded natural gas, with bitcoin mining as an early use case.

Crusoe is developing an AI campus at the Lancium Clean Campus in Abilene, Texas, planned for 1.2 GW, and in May 2025 it secured $11.6 billion in debt and equity to expand the site from two to eight buildings.

For this project, it is reported that Crusoe’s direct customer is Oracle and that OpenAI is Oracle’s customer; the Abilene campus is tied to OpenAI’s Stargate program;

OpenAI later announced an additional 4.5 GW Stargate partnership with Oracle that references the Abilene Stargate I site. Crusoe also expanded in-house manufacturing capability through the acquisition of Easter-Owens Electric in 2022.

Crusoe History:

  • In July 2025 announced a 1.8 GW AI data center campus with Tallgrass near Cheyenne, Wyoming.
  • In May, 2025, secured $11.6 billion in debt and equity to expand the Abilene, Texas campus to eight buildings, with Crusoe noting Oracle as the direct customer and OpenAI as Oracle’s customer for the site.
  • In March 2025 began construction on the second phase of the Abilene, Texas campus to bring total planned capacity to 1.2 GW.
  • In April 2022 raised Series C financing that included plans to launch the CrusoeCloud platform for high performance computing.
  • In June 2022 acquired Easter-Owens Electric to vertically integrate modular data center manufacturing.
  • Founded in 2018 as Crusoe Energy Systems to mitigate gas flaring by powering onsite computing, including bitcoin mining.
0
Facilities
0
Markets

News

Read Crusoe Ends $1.25B Boom Supersonic Turbine Order for AI Data Centers
[Crusoe](https://baxtel.com/data-centers/crusoe) has dropped its $1.25 billion launch order for Boom Supersonic's Superpower gas turbines, ending a plan to power AI campuses with turbines derived f...

Crusoe Ends $1.25B Boom Supersonic Turbine Order for AI Data Centers

September 26, 2026 Crusoe

Crusoe has dropped its $1.25 billion launch order for Boom Supersonic's Superpower gas turbines, ending a plan to power AI campuses with turbines derived from the engine behind its Overture supersonic airliner. Boom founder and CEO Blake Scholl said on Friday that the two Denver companies are no...

Read more
Read More News

Ready to Level up Your