US developers started construction on 8.4 gigawatts of US data center capacity in the third quarter, Cleanview says. The research firm's November 17 analysis puts the quarter 28% below the record second quarter. Cleanview counted 65
Featured: Structural steel and foundation work taking shape on a large-scale data center construction site.buildings started from July through September, against 96 in the prior quarter.
Cleanview puts the second quarter at a record 11.7 GW. Data Center Dynamics reported 11.2 GW for the prior quarter, a figure that differs from Cleanview's count. The third quarter was still the third-largest in Cleanview's series and 55% above the same period in 2025, the first quarterly decline since the first quarter of 2025.
Starts rebounded in October to 4.6 GW across 33 buildings, nearly double October 2025 and the second-biggest month on record after June. Three campuses supplied 1,631 MW, about 35% of the month's total. Nscale started 720 MW at its Monarch campus in West Virginia for Anthropic, Related Digital started 461 MW at Stargate Michigan for Oracle and OpenAI, and Crusoe started 450 MW at its Abilene, Texas, campus for Microsoft.
Developers started 38 GW in the 12 months through October, double the previous 12 months, Blockspace reported. Cleanview counts 58 GW under construction, close to the 65 GW already operating, and estimates buildings started in 2026 will cost about $1 trillion to build and equip.
Cleanview dates a construction start to the month vertical work begins, meaning foundation and steel rather than land clearing. The dataset covers 1,338 buildings on 473 campuses and measures facility power. It counts hyperscale, colocation, enterprise and crypto facilities together.
"Construction slowed this summer, but developers are still starting data centers at twice last year's pace," said Michael Thomas, founder and CEO of Cleanview. "One month doesn't make a trend. But if November and December match October, the fourth quarter will set a new record at about 14 GW," Thomas wrote.
Texas leads states with 9.8 GW started in the last 12 months, ahead of Virginia at 4.5 GW and Louisiana at 2.8 GW. Amazon AWS started the most capacity among developers at 4.6 GW, followed by Google at 4.1 GW and Meta at 3.9 GW.
Nine states with a governor or governor-elect who has promised or imposed a pause hold 41% of planned US capacity, Cleanview says. The firm did not attribute the third-quarter decline to a specific cause. [MLQ](https://mlq.ai/news/us-data-center-construction-starts-fell-28-in-the-third-quarter-after-a-record-spring-cleanview-says) reported that Loudoun County, Virginia adopted a pause on new approvals while Texas has resumed issuing data center permits.
Baxtel tracks more than 6,100 data center facilities in the United States, operated by 985 providers, with Amazon AWS the largest at 415 sites and Google at 134.