Patmos has closed on a former Walmart Supercenter in Fairfield, Alabama, for a data center campus that starts at 20 MW. The Kansas City company announced the acquisition on Nov. 13, after Baxtel reported the Fairfield proposal in July. Patmos Fair
Featured: News coverage photo documenting the former Walmart retail building and surrounding 16-acre site.field LLC paid $32 million for the 205,000-square-foot building, according to Jefferson County Probate Court records cited by WVTM 13.
Patmos develops and will operate the campus. The seller was 7201 Aaron Aronov Drive LLC, an entity tied to Safe Space Cos., a redevelopment firm based in New Iberia, Louisiana. That company bought the property for $1.95 million in 2022, WVTM reported. Alabama Power will serve the campus under terms the two sides have agreed to. Patmos says it will pay the full cost of that electric service, so the expense is not shifted to other Alabama Power customers. Alabama lawmakers passed SB270 this year, which requires the largest data centers to cover the power costs they create, Yellowhammer News reported.
The building at 7201 Aaron Aronov Drive sits on 16 acres next to Western Hills Mall and has been vacant since Walmart closed it in 2016. Patmos says its Fairfield site will start at 20 MW, with up to 50 MW of utility capacity available for later expansion. The campus is designed for artificial intelligence, high-performance computing, colocation and other web services. The project is expected to create about 50 jobs, 1819 News reported.
"We don't build data centers in the traditional sense... We also retrofit existing buildings, so we're not destroying local farmland," said John Johnson, CEO of Patmos. Patmos converted a former Kansas City newspaper printing plant into a high-density data center and cites that project as the model for Fairfield.
The purchase followed months of opposition. The Fairfield City Council passed a moratorium on future data center projects in July. Residents protested outside City Hall in October over a possible $150 million C-PACE financing arrangement, according to WVTM 13. Residents of the nearby Belwood community say they were not consulted before the sale. "We want a real world. We don't want a digital world," said Thelma Coleman, a Willow Brook Road resident, in an interview with WVTM 13.
Patmos says it is working with Alabama Power on a phased electrical infrastructure plan for the site. Initial operations are expected to begin in May 2027. Baxtel counts 12 data center facilities in the Birmingham market, led by DC BLOX with two sites, and two Birmingham data centers are under construction.