Published in NTT

NTT files for planning permission in Gainesville, Virginia for 336MW campus

Jun 26, 2023 | Posted by MadalineDunn

In Prince William County, NTT has filed for permission for a joint Federal and State permit from the Norfolk District of the US Army Corps of Engineers for a 336MW data center campus. 

The permit application, NTT VA10, outlines the project is named Grove at Gainesville and includes plans to build four two-story data centers on around 104 acres at 14210/14300 John Marshall Highway in Gainesville, offering more than two million square feet (185,800 sqm) of data center space. The first two-story building is set to open in the second quarter of 2024.

Documents indicate that the project would impact 2.2 acres of waters currently under the responsibility of the Army. Two species of local bat and one type of butterfly could also be impacted. 

According to reports, NTT had already announced plans for expansion in Gainsville, although details on the location were not shared; plans for data center development on the site were being formulated a year prior to NTT's announcement. It’s believed that AWS may be the customer of the data center. 

At full build-out, the site will be the AWS' largest campus in the US.


NTT has 136 sites in 18 regions.

Grand Opening of e-shelter's AMS1 site
Posted in NTT Amsterdam 1 Source: e-shelter
First data center in the Netherlands for e-shelter
Posted in NTT Amsterdam 1 Source: e-shelter
Rendering of E-Shelter's Facility in Dagenham
Posted in NTT London 1 (Dagenham) Source: e-shelter
Entrance Gate
Posted in NTT Berlin 1 Source: e-shelter
Outside of Frankfurt3
Posted in NTT Frankfurt 3 Source: e-shelter
Side of the Facility
Posted in NTT Frankfurt 3 Source: e-shelter
Exterior
Posted in NTT Frankfurt 3 |
Generator
Posted in NTT Frankfurt 3 |
Under Construction
Posted in NTT Frankfurt 3 Source: e-shelter
Under Construction in 2014
Posted in NTT Frankfurt 3 Source: e-shelter
Under Construction in 2014
Posted in NTT Frankfurt 3 Source: e-shelter
Generators
Posted in NTT Frankfurt 3 |
Empty Colocation Room Ready for a Deployment
Posted in NTT Frankfurt 3 |
Modern Style in the Customer Area
Posted in NTT Frankfurt 3 Source: e-shelter
Phase 1 of e-shelter's Frankfurt 4 datacenter nearing completion in May 2019
Posted in NTT Frankfurt 4 |
Progress on LON1 as of May 2019
Posted in NTT London 1 (Dagenham) Source: e-shelter
Rendering of e-shelter's fourth facility in FRA
Posted in NTT Frankfurt 4 Source: e-shelter
Outside
Posted in NTT Frankfurt 1 Campus Source: Investa.de
Building H was finished in November 2017 and has 17,797 sqm
Building H was completed in 9 months
Posted in NTT Frankfurt 1 Campus Source: Drees & Sommer
Small field next to e shelter's facility in Rümlang
Posted in NTT Zurich 1 |
View from Hofwisenstrasse road
Posted in NTT Zurich 1 |
Rupprecht Rittweger, e-shelter founder and CEO, is second from the right.
Frankfurt 4 Launch Event
Posted in NTT Frankfurt 4 Source: e-shelter
Lego kit of e-shelter's FRA 1 Campus
Posted in NTT Frankfurt 1 Campus Source: e-shelter
Outside of e-shelter's Munich 2 facility
Posted in NTT Munich 2 |
Munich 2 while under construction
Posted in NTT Munich 2 Source: e-shelter
Rendering of "Indonesia Jakarta 3" data centre
Posted in NTT Jakarta 3 (JK3) Source: NTT
Exterior
Posted in NTT VA1 |
Outside of Nodia facility
Posted in NTT: Noida 1 |
Netmagic Chennai
Posted in NTT Chennai DC1 |
Rendering of NTT SV1
Posted in NTT Silicon Valley SV1 Source: RagingWire
2019 Rendering of OS7
Posted in NTT Osaka 7 |
NTT Phoenix 7 Building Campus overview
Posted in NTT Phoenix Campus Source: NTT
Generators on the roof at MAD1
Posted in NTT Madrid 1 |
MAD1 Entrance
Posted in NTT Madrid 1 |
Exterior
Posted in NTT Madrid 1 |
Campus view showing VA3 to VA9
NTT Ashburn Campus Overview
Posted in NTT Ashburn Campus |
150,000 square foot VA1 data center is an EPA ENERGY STAR certified facility with 14.4 MWs of high density critical IT power
Layout Diagram of VA1 Building
Posted in NTT VA1 Source: Ragingwire
HH1
Posted in NTT Hempstead 1 |
Outside of HH2
Posted in NTT Hempstead 2 |
Drone shot of HH3
Posted in NTT Hempstead 3 |
Rendering of HH4
Posted in NTT Hempstead4 |
Outside of SL2
Posted in NTT Slough 2 |
External cooling plant
Posted in NTT Osaka 5 |
Seismic Damper
Posted in NTT Osaka 5 |
NAV1A in Mahape
Posted in NTT NAV1A |
DC7 built in 2020
Posted in NTT Chandivali DC7 |
DC6
Posted in NTT Chandivali DC6 |
Birdseye view of the NTT's first data center in South Africa
Posted in NTT Johannesburg 1 |
Exterior of NTT's 2nd data center in Marienpark
Posted in NTT Berlin 2 (Marienpark) |
Rechenzentrum Berlin 2 - NTT
Posted in NTT Berlin 2 (Marienpark) |
NTT HI2 data center under construction
Posted in NTT HI2 Source: Lewis
Rendering od NTT's Paris Campus
Posted in NTT: Paris 1 Source: Logistics Capital Partners
NTT Global's Corbeil Paris Data Center Campus
Posted in NTT: Paris 1 Source: Logistics Capital Partners
NTT Global's Corbeil Paris Data Center Campus
Posted in NTT: Paris 1 DC2 Source: Logistics Capital Partners
NTT Global's Corbeil Paris Data Center Campus
Posted in NTT: Paris 1 DC3 Source: Logistics Capital Partners
NTT Berlin-2 Data Center Campus in Germany
Posted in NTT: Berlin 2B Source: NTT
NTT's site plan for the Gainesville property
Posted in NTT Gainesville VA Campus Source: US Army Corps of Engineers | NTT
The first of four data centers of NTT Gainesville Campus under construction
Posted in NTT: VA11 Source: NTT
NTT plans to develop a data center campus on the former barracks site in Neirstein
Posted in NTT: Nierstein Source: Google Maps
Rendering of NTT's NAV2 Campus in Navi Mumbai, India
Posted in NTT: NAV 2 Source: Panchshil
Rendering of NTT Ho Chi Minh City data center in Vietnam
Posted in NTT: Ho Chi Minh City 1 Source: NTT
Second Mesa campus planned by NTT with 173 acres land acquisition
Posted in NTT: Pacific Proving Tech Park Source: Google Maps
NTT launched data center in Bengal Silicon Valley Tech Hub, Kolkata
Posted in NTT: Kolkata Campus Source: LinkedIn post of NTT Global Data Centers
Rendering of NTT's Bengaluru 4 Campus
Posted in NTT: Bengaluru 4 Campus Source: NTT
NTT's VA6 Data Center under construciton
Posted in NTT: VA6 Source: NTT

Ready to Level up Your
Data Center Strategy?