[Merlin Properties](https://baxtel.com/data-centers/merlin-properties) has paused work on two buildings at its [Bilbao-Arasur data center campus](https://baxtel.com/data-center/merlin-bilbao-arasur...

Merlin Pauses Two Bilbao Data Center Buildings, Cuts MEGA Plan to 704MW

Abdul-Rahman Oladimeji

Abdul-Rahman Oladimeji

November 19, 2026

Merlin Properties has paused work on two buildings at its Bilbao-Arasur data center campus after failing to secure an electricity supply for them. The suspension covers Arasur 4 and Arasur 5 in Álava, in Spain's Basque Country. Chief executive Ismael Clemente confirmed the halt at Merlin's first-nine-months results presentation, where the company reported 160 MW of IT capacity leased and raised its 2026 profit guidance.merlinproperties.comFeatured: Wide exterior view of the operational data center facility at the Bilbao-Arasur campus.

Merlin owns the Bilbao-Arasur campus and develops it through MERLIN Edged, its data center division with Edged Energy. When it opened the first building, Merlin said the campus would have six buildings and up to 300 MW of IT capacity, with the first two phases at 118 MW. Merlin has one building operating at Arasur, with a second due online before the end of the year and a third due in 2027, DCD reported.

The two suspended buildings were to draw part of their power from Solaria, a Merlin energy partner in the region. Administrative problems at several Solaria solar projects compromised that supply. Crónica Vasca reported that the Basque government's industry department denied authorization for 19 Solaria solar parks in Álava in July.

The pause landed as Merlin recalculated the cost of Spain's proposed data center rules. A draft royal decree published on Aug. 27 would tie grid access for facilities with 1 MW or more of access power to energy, water, resilience and digital sovereignty requirements. The government sent a revised text to the Council of State on Oct. 26 after more than 600 submissions, the law firm Garrigues reported. Merlin has set aside €863 million in additional capital spending, mostly for batteries, equal to 11.3% of its planned investment, Demócrata reported. The company also cut its MEGA Plan from 724 MW to 704 MW of IT capacity because of the Arasur supply problem. "We have assumed that the royal decree is in force and that it will continue to be so in the foreseeable future," Clemente said.


Merlin is working with Solaria to shift the demand to parts of Spain with more self-consumption capacity, DCD reported. The company is also considering moving some development to Portugal and Madrid and adding a second project in Aragón, and it said its Cáceres campus at Navalmoral de la Mata could be affected too. Baxtel counts 14 data center sites in the [Bilbao](https://baxtel.com/regions/bilbao) market, which it ranks the second-largest in [Spain](https://baxtel.com/regions/spain), with Merlin Properties holding one and Edged Energy three. Clemente said the royal decree could reach the Council of Ministers for approval on Nov. 20 or Nov. 24, or later in December after Spain's general election on Nov. 29.