Published in Grand Rapids MI

Gerald R. Ford International Airport is building an operations center in Grand Rapids, Michigan

Jun 30, 2021 | Posted by Abdul-Rahman Oladimeji

Gerald R. Ford International Airport is building a new operations and communications center, which includes, a data center in Grand Rapids, Michigan. The project will cost the Company $7.7 million. Gerald R. Ford International airport says the new facility will be on the east side of the airport’s campus. The facility is scheduled to be completed in June 2022.

CEO and president of the Airport, Tory Richardson, said the new operations center would help improve communication, efficiencies, and collaboration for the airport’s teams. He added that without the team, the airport would not be able to provide the high-quality and excellent safety track record the airport is famous for. The new building will be an 11,600 square feet facility and it is designed to withstand harsh weather conditions.

There are 12 data centers in Grand Rapids MI.

Rendering of the Switch PYRAMID
Posted in Switch: Grand Rapids (The Pyramid Campus) Source: Switch.com
Rendering of the Supernap Pyramid Campus
Posted in Switch: Grand Rapids (The Pyramid Campus) |
Location Total SqFt Gross SqFt Power (MW)
US Signal: MI01 Grand Rapids East 40,000 SqFt
NN
US Signal Grand Rapids South 20,000 SqFt
NN
123NET: DC4 4,000 SqFt
3,500 SqFt
NN
Switch: Grand Rapids 2 400,643 SqFt
Switch: Grand Rapids 1 312,000 SqFt
NN

Ready to Level up Your