Daibiru, Sankei Building and Osaka Gas Urban Development will take stakes in the company that owns a 15MW data center in Ishikari City, Hokkaido. The three developers announced the decision
Featured: Wide exterior visual of the 15MW Ishikari Renewable Energy Data Center 1 in Hokkaido developed by Tokyu Land.on November 18, according to Sankei Building's press release. Tokyu Land Corporation and Flower Communications developed the renewable-powered facility and continue as project managers.
The three are taking stakes in Ishikari Renewable Energy Data Center No. 1 LLC, the project company behind the facility. Agility Asset Advisers serves as asset manager. The developers did not disclose financial terms. For Daibiru and Osaka Gas Urban Development, the deal is a first move into the data center business, Data Center Dynamics reported.
The facility occupies about 10,065 square meters in the Ishikari Bay New Port area and has 15,000 kW of power receiving capacity. Construction finished on March 27, 2026, and service began on August 1, 2026. All of its electricity comes from renewable plants in Ishikari City, delivered over private power lines under an onsite power purchase agreement that Tokyu Land signed with the city in March 2024.
BroadBand Tower operates a data center base inside the building, and GMO Internet plans to open a GMO GPU Cloud site in part of that floor space within 2026, according to GMO Internet.
Daibiru said the investment is part of an effort to "capture new business opportunities in this growth sector and build up its expertise in the data centre business." Daibiru, a subsidiary of shipping group Mitsui O.S.K. Lines, was founded in 1923 and has concentrated on offices in Osaka and Tokyo. Sankei Building, established in 1951, opened its first data center, the Optage Sonezaki Data Center in Osaka, in 2025, as Mingtiandi reported. Osaka Gas Urban Development is the real estate and urban development arm of the Daigas Group.
Baxtel tracks 4 data center facilities in Hokkaido, operated by three providers and led by SoftBank Corp., whose Sapporo site is the region's largest at 1.2 MW. Daibiru and Sankei Building expect to complete their investments on March 31, 2027.