Travagliato Data Center

Latest Podcast Via Averolda
Withdrawn
Project cancelled before construction
Operated by: East Gate

Travagliato Data Center

Site planned for 2028 and has expansions through 2029
Utility Provider: e-distribuzione
Lot Size: 32 acres

East Gate S.r.l., a Brescia company, proposed an AI-focused data center on about 13 hectares off Via Averolda in Travagliato. The site lies in an industrial zone near the Ospitaletto border, about 1 km from the Travagliato exit of the A35. The plan, by urban planning firm The Blossom Avenue Partners, had one two-storey building, a substation, a fire station and parking. Travagliato opposed the project, and East Gate withdrew its implementation plan in September 2026. No new filing has been reported.

Site History

  • 2026-09: East Gate withdraws its implementation plan, and the province moves to archive the grid connection request.
  • 2026-08: The province suspends the grid connection file, and Travagliato confirms its opposition.
  • 2026-07: East Gate presents a scaled-down plan with more than €11 million for the comune.

Map and Nearby Locations

Via Averolda ( 25039 Travagliato, Province of Brescia )
East Gate Sites
Nearby Facilities

Travagliato Data Center Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Travagliato Data Center

Distance Site About
3.18 miles Retelit: Brescia
Retelit runs a small data center on Via Francesco Perotti in the industrial zone of Brescia.
4.45 miles Carrier Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
5.58 miles A2A: Brescia Lamarmora
A2A plans a data center for AI and colocation inside its Lamarmora energy complex in Brescia, powered by its waste-to-energy plant.
5.63 miles Scaleway: Brescia
Scaleway, which acquired Qarnot in 2026, runs a waste-heat data center pilot inside A2A's Lamarmora power plant in Brescia, feeding the city's district heating network.

Operating Company

Operated by: East Gate

East Gate S.r.l. is a privately held company based in Brescia. Filippo Signoroni is CEO.

In December 2025 East Gate filed an implementation plan with the Comune of Travagliato for a data center campus in the town's industrial zone, designed by The Blossom Avenue Partners, and applied for a grid connection. The Comune issued a negative opinion in August 2026, and East Gate withdrew the plan in September 2026.

East Gate History:

  • In September 2026, East Gate withdrew its implementation plan for the Travagliato data center.
  • In August 2026, the Comune of Travagliato issued a negative opinion on the project.
  • In December 2025, East Gate filed an implementation plan with the Comune of Travagliato for a data center campus.
0
Facilities
0
Markets

News See all

Read CBRE Forecasts Milan Will Add 255MW and Pass Dublin as Europe's Fifth Market
CBRE forecasts 255MW of new data center capacity in Milan by 2028, which would move the city ahead of Dublin as Europe's fifth-largest market. The forecast appears in CBRE's [Q3 2026 European Data ...

CBRE Forecasts Milan Will Add 255MW and Pass Dublin as Europe's Fifth Market

November 17, 2026 Milan

CBRE forecasts 255MW of new data center capacity in Milan by 2028, which would move the city ahead of Dublin as Europe's fifth-largest market. The forecast appears in CBRE's Q3 2026 European Data Centres report, which puts Milan and Dublin about 100MW of operational capacity apart at the...

Read more
Read Milan Data Center Protest Draws Over 1,000 As Lombardy Plans Stricter Law
More than 1,000 people gathered in Piazza della Scala in Milan on Oct. 10 to oppose new data center construction in Lombardy, [Il Giorno](https://www.ilgiorno.it/milano/cronaca/data-center-protesta...

Milan Data Center Protest Draws Over 1,000 As Lombardy Plans Stricter Law

November 10, 2026 Milan

More than 1,000 people gathered in Piazza della Scala in Milan on Oct. 10 to oppose new data center construction in Lombardy, Il Giorno reported. The rally was the first national demonstration called by the National Network of Stop Data Center Committees. Organizers want the national government...

Read more
Read Greenfield And Finsbury Infrastructure To Invest €360M In Milan Data Center
UK infrastructure developer Greenfield and Finsbury Infrastructure plan to invest up to €360 million ($418m) to develop a 36MW data center east of Milan, Italy. Greenfield has already secured 80MW ...

Greenfield And Finsbury Infrastructure To Invest €360M In Milan Data Center

September 08, 2026 Milan

UK infrastructure developer Greenfield and Finsbury Infrastructure plan to invest up to €360 million ($418m) to develop a 36MW data center east of Milan, Italy. Greenfield has already secured 80MW of power capacity for the site, which will support AI, cloud, and enterprise workloads while...

Read more
Read Magnora Secures Milan-Area Land for 30 MW Data Center, Its Second Italy Project
Magnora Secures Milan-Area Land for 30 MW Data Center, Its Second Italy Project

Magnora Secures Milan-Area Land for 30 MW Data Center, Its Second Italy Project

May 18, 2026 Magnora

Norwegian renewables and data center developer Magnora ASA has secured land for a new 30 MW data center project in the Milan area, the company announced on Monday. The wholly owned project is Magnora's second in Italy and brings its data center development portfolio to 585 MW gross and 460 MW...

Read more
Read Irideos is expanding its Avalon campus in Milan
Irideos is expanding its Avalon campus in Milan

Irideos is expanding its Avalon campus in Milan

October 01, 2021 Milan

Italian data center company Irideos has begun work on a new data center at its Avalon campus in the city of Milan. The new facility named Avalon 3 will have space for 500 racks across 37,700 square feet (3,500 square meters). It will also have 3.2MW of capacity. Irideos is building the new data...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Quotes
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.