Terawulf: Cayuga (Lake Hawkeye)

Latest Podcast Miliken Station
Under ConstructionPlanned
Multi-phase construction project
Operated by:

Terawulf: Cayuga (Lake Hawkeye)

Site planned for 2027 and has expansions through 2029
Ownership: Terawulf does not own the building.
Lot Size: 183 acres

Terawulf has secured an 80-year ground lease for a high-performance computing (HPC) and AI data center campus at the former Cayuga coal-fired power plant in Lansing, New York, a site also known as the "Cayuga data center campus".

TeraWulf plans to bring the first phase of this development online in 2026, using low-cost, predominantly zero-carbon power. The lease also includes purchase and sale options that can be exercised beginning in year 50.

Map and Nearby Locations

Miliken Station
Terawulf Sites
Nearby Facilities

Terawulf: Cayuga (Lake Hawkeye) Power Growth Over Time

Operational
Construction
Planned
Prospective
In Doubt
Withdrawn
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Terawulf: Cayuga (Lake Hawkeye)

Terawulf: Cayuga (Lake Hawkeye) Data Center Photos See all

Operating Company

Operated by:

TeraWulf is a cryptocurrency mining company that prioritizes sustainability by utilizing over 91% zero-carbon energy sources for its Bitcoin mining operations across the United States. TeraWulf aims to revolutionize energy-efficient cryptocurrency mining. By leveraging their expertise in development, engineering, and energy markets, they strive to establish an innovative paradigm that transforms zero-carbon electrons into cryptocurrency in an environmentally responsible manner.

29
Facilities
6
Markets

News See all

Read TeraWulf Seeks $3.5 Billion to Build Data Center for Anthropic
TeraWulf is seeking approximately $3.5 billion in debt financing to support construction of its Justified Data campus in Hawesville, Kentucky, which will be leased to AI company Anthropic. Accordin...

TeraWulf Seeks $3.5 Billion to Build Data Center for Anthropic

July 10, 2026 Terawulf

TeraWulf is seeking approximately $3.5 billion in debt financing to support construction of its Justified Data campus in Hawesville, Kentucky, which will be leased to AI company Anthropic. According to Bloomberg, Morgan Stanley is expected to lead the financing package, which is likely to include...

Read more
Read TeraWulf Purchases Kentucky Site for 1GW Data Center Campus
TeraWulf Purchases Kentucky Site for 1GW Data Center Campus

TeraWulf Purchases Kentucky Site for 1GW Data Center Campus

May 28, 2026 Terawulf

Crypto mining and AI infrastructure company TeraWulf is growing its presence with plans for a second facility in Kentucky. The company this week revealed it has acquired a hyperscale high-performance computing (HPC) development site in Eastern Kentucky. Purchased from Industrial Equity Partners,...

Read more
Read TeraWulf Buys Site in Kentucky for 1GW Data Center Campus
TeraWulf Buys Site in Kentucky for 1GW Data Center Campus

TeraWulf Buys Site in Kentucky for 1GW Data Center Campus

May 27, 2026 Terawulf

TeraWulf is expanding its presence in Kentucky with the acquisition of a second planned site for hyperscale high-performance computing. The Nasdaq-listed cryptomining and AI infrastructure firm announced it has acquired the Muskie Data Campus in Eastern Kentucky from Industrial Equity Partners....

Read more
Read Cannabis Company Wants to Turn Former Golf Course in New York into Data Center
Cannabis Company Wants to Turn Former Golf Course in New York into Data Center

Cannabis Company Wants to Turn Former Golf Course in New York into Data Center

April 02, 2026 New York

A cannabis firm is exploring plans to redevelop a former golf course in New York into a data center campus. OTC-listed Weed Inc. said it aims to repurpose its subsidiary’s 44-acre Sugar Hill Golf Course site in Chautauqua County, near Lake Erie, though full project details have not been...

Read more
Read TeraWulf Completes Latest Data Center at New York’s Lake Mariner Campus
TeraWulf Completes Latest Data Center at New York’s Lake Mariner Campus

TeraWulf Completes Latest Data Center at New York’s Lake Mariner Campus

March 20, 2026 Terawulf

Cryptomining company turned data center developer TeraWulf has topped out its newest facility in New York.“Today we topped out CB4, marking the final structural beam placed - all thanks to the crews who brought this build to life,” the company announced on LinkedIn this week. “What stands above...

Read more
Read More News

Podcasts See all

See More Podcasts

Documents See all

Ready to Level up Your
Data Center Strategy?