Rivington Energy: Avonmouth

Latest Podcast Former Polymers Recycling Facility, Severn Road
In Doubt
The development is facing regulatory or community opposition
Operated by:

Rivington Energy: Avonmouth

Year Planned: 2027
Utility Provider: National Grid Electricity Distribution
Lot Size: 14 acres

Rivington Energy, working with Viridor, has applied to Bristol City Council to convert the former polymers recycling facility at Viridor's Avonmouth energy recovery facility into a data centre for AI workloads. The plans keep the existing building, add a three-storey plant gantry for standby generators, switchrooms and cooling, and place a new grid substation and fuel-cell energy centre in the north-west corner of the site. Power would come from the grid and by direct wire from the adjoining energy-from-waste plant. Viridor has said the facility could run as early as 2027 if approved. The scheme is one of four sites in a Viridor and Rivington partnership at energy-from-waste plants.

The application faces strong opposition. More than 4,000 objections have been lodged, Natural England has advised refusal over bird disturbance on the Severn Estuary, and the Environment Agency has objected on flood risk, contamination and groundwater grounds. The council has ruled that an Environmental Impact Assessment is required, so no decision can be made until an Environmental Statement is submitted.

Site History

  • September 2026: Bristol City Council issued a screening opinion requiring an Environmental Impact Assessment.
  • June 2026: Rivington Energy submitted a full planning application for the change of use.
  • June 2026: Viridor and Rivington Energy announced a partnership to develop data centres at energy-from-waste sites, including Avonmouth.

Map and Nearby Locations

Former Polymers Recycling Facility, Severn Road ( Viridor Avonmouth ERF, Avonmouth )
Rivington Energy Sites
Nearby Facilities

Rivington Energy: Avonmouth Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Rivington Energy: Avonmouth

Distance Site
3.76 miles nLighten: Bristol BRS1
4.80 miles Wavenet: Bristol
8.56 miles University of Bristol: Isambard-AI
8.89 miles Carrier-Neutral Data CenterInterested in this information?Contact us
8.95 miles Carrier-Neutral Data CenterInterested in this information?Contact us
9.01 miles Carrier-Neutral Data CenterInterested in this information?Contact us
9.03 miles Carrier-Neutral Data CenterInterested in this information?Contact us
9.08 miles Carrier-Neutral Data CenterInterested in this information?Contact us
9.14 miles Carrier-Neutral Data CenterInterested in this information?Contact us
12.78 miles Era4: Newport, South Wales
15.72 miles Station AlphaInterested in this information?Contact us
15.73 miles Vantage CWL13
15.82 miles Vantage: CWL12
15.96 miles Vantage Cardiff CWL1
16.02 miles HubInterested in this information?Contact us
16.03 miles GammaInterested in this information?Contact us

Operating Company

Operated by:
0
Facilities
0
Markets

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Quotes
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.