Misae: North America Data Center

Latest Podcast 1892 County Road 428
Planned
Future facility in planning stage
Operated by:

Misae: North America Data Center

Year Planned: 2028
Utility Provider: Guadalupe Valley Electric Cooperative
Lot Size: 525 acres

Misae Investments is developing the North America Data Center on about 525 acres of a ranch near Stockdale in Wilson County, southeast of San Antonio. The campus is planned in phases beside an on-site natural-gas power plant, with a fuel-cell alternative, and the company has also requested a grid interconnection. Misae plans a large solar project on adjoining land. The developer says it will not operate the data center itself, and it targets first operation in 2028 after construction starts in 2027.

Site History

  • March 2026: The founder answers local concerns about the project.
  • January 2026: The state permits the on-site gas power plant.
  • November 2025: Misae announces the data center.

Map and Nearby Locations

1892 County Road 428
Misae Investments Sites
Nearby Facilities

Misae: North America Data Center Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Misae: North America Data Center

Distance Site About
16.84 miles Legacy: San Antonio
Legacy Investing is developing an AI-focused data center at the former San Antonio Karting Complex in Marion, east of San Antonio, for service from late 2027.

Operating Company

Operated by:

Misae Investments is a privately held Texas energy developer founded in 2016 by Dr. Miguel Alejandro Oneto, a physician and entrepreneur from McAllen, Texas. It has offices in Dallas and Boca Raton, Florida, and also operates under the Misae Solar and Misae Energy names.

The company finds and buys land, secures grid connections and permits, and sells ready-to-build projects to investors who build and operate them. It developed solar parks in Childress and Leon counties. In Wilson County, near Stockdale, it is developing the Misae Energy Hub, a data center campus with a permitted on-site natural gas plant and a solar project on adjoining land.

Misae Investments History:

  • In November 2025, Misae's plan for an AI data center in Wilson County, Texas, was first reported.
  • In April 2025, Greenalia secured $388 million in financing for Misae Solar Park II in Childress County.
  • In May 2024, Ferrovial agreed to acquire the Leon Solar Park project in Leon County.
  • In 2018, Misae sold the Childress Solar Park project to Copenhagen Infrastructure Partners.
  • Founded in 2016 in Texas.
0
Facilities
0
Markets

News See all

Read Microsoft wants to build five more data centers in San Antonio, Texas
Baxtel

Microsoft wants to build five more data centers in San Antonio, Texas

July 13, 2021 San Antonio

According to recent documents filed with the Texas Department of Licensing and Regulation, Microsoft has applied to build five more data centers in San Antonio, Texas. The data centers will have a total space of 350,000 square feet. It will also cost over $200 million. The construction of the...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Quotes
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.