Maxland: Kulim

Latest Podcast Jalan Hi-tech 6/1
Withdrawn
Project cancelled before construction
Operated by:

Maxland: Kulim

Short Code: KLM1
Year Built: 2026
Utility Provider: Tenaga Nasional Berhad
Ownership: Maxland Berhad does not own the real estate.
Lot Size: 5 acres

Maxland, a Malaysian timber company, and Global Data Centre planned a data center in Kulim Hi-Tech Park. Maxland leased the plot for 60 years, and the partners agreed to fund a joint venture with RM24 million. Maxland rescinded the leases after a strategic review, before any construction.

Site History

  • May 2026: Maxland rescinds the leases.
  • January 2025: Maxland and Global Data Centre sign the joint venture.
  • December 2024: Maxland leases the plot and signs a memorandum with Global Data Centre.

Map and Nearby Locations

Jalan Hi-tech 6/1 ( Kulim Hi-tech Park, 09000 Kulim )
Maxland Berhad Sites
Nearby Facilities

Maxland: Kulim Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Maxland: Kulim

Distance Site
12.70 miles Carrier Data CenterInterested in this information?Contact us
19.92 miles CSF P. Pinang Service Centre

Operating Company

Operated by:

MAXLAND BERHAD is principally an investment holding company with several wholly-owned subsidiaries.

Since its inception in 1992, MAXLAND has developed a strong presence in the Malaysian timber industry. Today the Company has successfully established an effective integrated upstream and downstream operation while maintaining a strong corporate responsibility towards the environment in which it operates.

MAXLAND was listed on the Second Board of the Bursa Malaysia in 2001 and was upgraded to the Main Board in 2004.

The Company’s long-term vision is to be a leading player in the Malaysian timber and wood-based products industry.

0
Facilities
0
Markets

News See all

Read SoftBank, Grab And PETROS Sign $1.85B JDA For 5GW Malaysia Buildout
[SoftBank Group](https://baxtel.com/data-centers/softbank-corp), Grab and PETROS have signed a joint development agreement to build AI infrastructure in [Malaysia](https://baxtel.com/regions/malays...

SoftBank, Grab And PETROS Sign $1.85B JDA For 5GW Malaysia Buildout

November 11, 2026 Softbank Corp.

SoftBank Group, Grab and PETROS have signed a joint development agreement to build AI infrastructure in Malaysia, advancing the October framework agreement between the three companies. The agreement carries US$1.85 billion in combined seed capital and a target of five gigawatts or more of AI...

Read more
Read Google To Invest $15 Billion In Malaysia Data Center Expansion
[Google](https://baxtel.com/data-centers/google) will invest $15 billion in Malaysia to build new data center campuses, the company said in [its Nov. 4 announcement](https://www.googlecloudpresscor...

Google To Invest $15 Billion In Malaysia Data Center Expansion

November 04, 2026 Google

Google will invest $15 billion in Malaysia to build new data center campuses, the company said in its Nov. 4 announcement. The two-year program runs through 2027 and 2028 and expands on the $2 billion the company committed in 2024. It follows Baxtel's Nov. 2 report on Google's $160...

Read more
Read Google Funds $160M Water Plant for Malaysia Data Center Campus
Google will fund US$160 million of shared water infrastructure in Negeri Sembilan, Malaysia, for its planned Port Dickson data center campus. [Google](https://www.googlecloudpresscorner.com/2026-11...

Google Funds $160M Water Plant for Malaysia Data Center Campus

November 02, 2026 Google

Google will fund US$160 million of shared water infrastructure in Negeri Sembilan, Malaysia, for its planned Port Dickson data center campus. Google announced the commitment on November 2. Gamuda Berhad will build an off-river storage reservoir and a water treatment plant that will deliver 65...

Read more
Read Malaysia Requires Data Centers To Source 30% Renewable Energy
Malaysia's government has approved a requirement for data centers to source at least 30 percent of their power from renewable energy. Deputy Prime Minister Datuk Seri Fadillah Yusof told the Dewan ...

Malaysia Requires Data Centers To Source 30% Renewable Energy

October 29, 2026 Malaysia

Malaysia's government has approved a requirement for data centers to source at least 30 percent of their power from renewable energy. Deputy Prime Minister Datuk Seri Fadillah Yusof told the Dewan Rakyat on October 27 that the rule applies to a data center's total capacity or its energy...

Read more
Read DayOne Adds $3.67 Billion Johor Financing, Bank Platform Hits $7.3 Billion
A seven-bank consortium has added RM15 billion, about US$3.67 billion, to [DayOne](https://baxtel.com/data-centers/dayone)'s Johor data center financing, lifting the Singapore-headquartered operato...

DayOne Adds $3.67 Billion Johor Financing, Bank Platform Hits $7.3 Billion

October 14, 2026 DayOne

A seven-bank consortium has added RM15 billion, about US$3.67 billion, to DayOne's Johor data center financing, lifting the Singapore-headquartered operator's debt platform in Malaysia's southern state to RM30 billion, or roughly US$7.3 billion. The lenders set out the upsizing in a...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Quotes
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.