Overview
Jämtland is an inland county in central Sweden, centred on Östersund. In 2023 EcoDataCenter announced a large campus at Verksmon outside the city, paired with greenhouses heated by server heat. In September 2025 it dropped the plan to concentrate on Dalarna, where it had powered land ready. Nothing was built.
The Market Today
Vostroblock mines bitcoin in a former floor factory in Bräcke. Its subsidiary Roofscapes plans a larger campus there with a connection to the 400 kV grid. In October 2026 Bräcke's municipal council approved selling Roofscapes more land, and a new local plan is under way.
Advantages
-
Grid room. Svenska kraftnät (Svk) maps more than 500 MW of free withdrawal capacity in Jämtland for 2026. It has allocated or reserved only 450 MW in the county for 2027 to 2035.
-
Lower tax. All of Jämtland qualifies for the Norrland deduction of 9.6 öre per kWh from the energy tax.
Challenges
-
Powered sites. In April 2024 Jämtkraft cancelled the groundwork tender at Verksmon. A full connection to the new grid was not due until late 2027, and EcoDataCenter said its customers no longer had time to wait.
-
Grid costs. In October 2026 Jämtkraft sued EcoDataCenter for about SEK 140 million in grid preparation costs.
Power and Policy
Jämtland lies in SE2. Jämtkraft, Östersund's municipal energy company, runs the grid around the city, and Härjeåns Nät serves Bräcke. After the campus fell through, Jämtkraft turned its grid plans to Uniper's planned fuel plant at Lugnvik.