Aster S.r.l. owns the land and is the plan's developer of record. XDC Properties, a Private Equity OperatorInterested in this information?Contact us data center developer, is named with Aster as client on the plan drawings. The plan places a two-storey data center and an office block, about 33,700 m² in all, on 6.8 hectares off Via Ruggero Leoncavallo. The building would stand about 19 m high, opposite the Coop and near the Parco delle Groane. A 132 kV underground cable from Terna's Bovisio station, about 8 km away, would supply the site. The planning agreement awaits the sale of some council-owned land inside the area, and residents' groups oppose the project.
Site History
-
2026-10: Cesate's town council approves the implementation plan, and about 1,000 people march against the project.
-
2026-07: The town council adopts the plan, and the province of Monza e Brianza authorises the 132 kV connection cable.
-
2026-02: Cesate exempts the plan from strategic environmental assessment.
-
2025-09: Aster S.r.l. files the implementation plan for a data center.