Gorilla Technology Group, the Nasdaq-listed AI infrastructure provider, is developing an AI data center campus in Korat (Nakhon Ratchasima), about 260 kilometers northeast of Bangkok. Gorilla has paid for its first land installment and now controls about 142 rai, with grid power allocated through dual redundant feeds and substation works under way. The campus is planned as four modular data halls, with an option for six, and Gorilla has said it will start building each hall only once a customer has signed.
The design targets a PUE of about 1.3 and an all-GB300 configuration at roughly 142 kW per rack. Gorilla plans to fund the campus with project-level debt and long-duration institutional capital, serving Thai and regional demand for large-scale AI compute.
Site History
- November 2026: Gorilla re-plans the campus as four modular halls on 142 rai and says construction follows customer signings.
- May 2026: Gorilla announces the Korat AI campus and pays the first land installment.