Fluidstack: Progress Park, Virginia

Under Construction
New facility under construction
Operated by:

Fluidstack: Progress Park, Virginia

Year Planned: 2027
Utility Provider: Appalachian Power
Lot Size: 99 acres

Fluidstack is building an AI data center on Lot 35 of Progress Park, a certified data center site east of Wytheville. Solis Arx announced the project in December 2025, and Fluidstack took it over in 2026. The site sits across Kents Lane from the Gradient substation, which Fluidstack is paying to upgrade. The nearest homes are more than a mile away.

The single building opens in phases. Fluidstack expects most construction to finish by the end of 2027. A closed-loop cooling system with air-cooled chillers uses about 2,000 gallons of water a day after an initial fill of about 400,000 gallons. Three backup generators provide emergency power. Wythe County provided the ungraded lot at no cost in return for an investment of over $1 billion. The project expects about 1,000 construction workers at peak and 75 permanent jobs.

Site History

  • October 2026: Fluidstack held a public open house. The building was under construction.
  • June 2026: Fluidstack briefed the Wythe County Board of Supervisors on its acquisition of Solis Arx.
  • December 2025: Solis Arx and Wythe County announced the AI computing campus. Work on the ungraded lot began.
  • 2024: The Joint Industrial Development Authority of Wythe County began working with a developer on a Progress Park data center.

Map and Nearby Locations

Kents Ln
Fluidstack Sites
Nearby Facilities

Fluidstack: Progress Park, Virginia Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Fluidstack: Progress Park, Virginia

Distance Site About
9.70 miles TAC: Wythe County
TAC Data Centers' planned hyperscale campus on about 1,000 acres in eastern Wythe County, Virginia, beside Interstate 81 exit 86 near the Pulaski County line. Plans call for nine to 11 single-story buildings.

Operating Company

Operated by:

Fluidstack accelerates the world’s most ambitious AI projects by removing the bottlenecks to compute. Partnering with leading AI labs, governments, and enterprises, the company deploys scaled infrastructure at speed to unlock a future of abundant intelligence.

0
Facilities
0
Markets

News See all

Read Fluidstack Starts Construction on 99-Acre Wythe County Data Center Campus
Fluidstack has begun construction on a 99-acre data center campus at Progress Park in Wythe County, Virginia, [WDBJ reported](https://www.wdbj7.com/2026/10/29/fluidstack-hosts-open-house-wythe-coun...

Fluidstack Starts Construction on 99-Acre Wythe County Data Center Campus

November 10, 2026 Fluidstack

Fluidstack has begun construction on a 99-acre data center campus at Progress Park in Wythe County, Virginia, WDBJ reported. Wythe County is the only locality in the New River Valley with a data center under construction, WSLS reported. The campus is called Solis Arx. Wythe County and the Joint...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.