EdgeConneX, owned by EQT, bought about half of the former Northvolt Ett battery plant site at Bergsbyn in Skellefteå from Lyten in 2026, including the DS4 building. DC01 converts DS4 and the neighbouring FA03 building into a data center. Skellefteå kommun granted the building permit in September 2026, together with a new two-storey building, DC02. Strip-out work in DS4 began in the summer of 2026 with Winthrop Technologies as main contractor, and the first phase is due in early 2028. EdgeConneX and Lyten take over Northvolt's grid connections from Skellefteå Kraft. The campus uses closed-loop water cooling without evaporation.
Site History
- October 2026: The kommun issued a start permit for foundation work.
- September 2026: Skellefteå kommun granted the building permit for DC01 and DC02.
- August 2026: Strip-out work was under way in DS4.
- February 2026: EdgeConneX announced plans for a data center campus of up to 1 GW on land bought from Lyten.