AtlasEdge unveils Leeds first Tier 3 standard data center. After acquiring the largest purpose-built data centre in Leeds in 2022, AtlasEdge has since invested more than £13 million to transform the site.
Technical stats
- Size: 11,000 sq ft of net technical capacity
- Total customer power: 3MW
- Percentage occupied: 10% (at time of re-opening in 2023)
- Networks available on site: 9 – BT, Virgin, SSE, Verizon, Gamma, CenturyLink (Level3), Cogent, TalkTalk, Metronet, euNetworks
- Standard power: 4-7kW per rack as standard, but flexibility to provide up to 20kW
- The facility was Former Hardy Fisher data centre, acquired by Atlas Edge in 2022
- Relaunched in 2023 further to a complete £13m refurbishment
- a high-quality, 200-rack, Tier 3 facility
Key features of the upgrade works include a second and fully diverse incoming power feed at 11kV with 3.4MW currently available, further generators to upgrade to n+n, separate UPS rooms, enhanced security fencing, and 24/7 on-site security.