Prometheus X Engie to Colocate Data Centers with Renewable Assets
September 01, 2025
Prometheus Hyperscale
Construction of the Wyoming Hyperscale White Box data center began in 2022 on a 58-acre plot near Aspen Mountain in Evanston, Wyoming. This project aims to set a new standard for environmentally-friendly, highly efficient data centers that also contribute positively to local communities.
The data center is being built on land owned by Thornock's family, which has been involved in ranching for 6 generations. The location benefits from ready access to renewable energy from nearby wind and solar farms.
The initial phase of the Evanston project is scheduled to become operational in the first quarter of 2026, marking the debut of its first facilities.
Wyoming Hyperscale has merged with Prometheus Hyperscale, expanding their initial project into plans for a massive 1 GW data center campus.
Previously known as Wyoming Hyperscale White Box.
We are members of a 6th generation ranching family combining senior executive level industrial real estate development experience with legacy land resources to sustainably satisfy parabolic demand for data center capacity. We are the developer of the Aspen Mountain Hyperscale Data Center Project [30MW] in the midst of four large-scale wind projects and one large-scale solar power project that together produce more than 500MW of renewable energy.
September 01, 2025
Prometheus Hyperscale
July 25, 2025
Wyoming
May 23, 2024
Prometheus Hyperscale
December 08, 2022
Wyoming
March 17, 2022
Wyoming
Mar 12, 2026
Eric Bell
World
Feb 05, 2026
Eric Bell
World
Jan 15, 2026
Eric Bell
Applied Digital
Jan 05, 2026
Eric Bell
Dallas
Sep 04, 2025
Eric Bell
Texas