Site planned for 2027 and has expansions through 2030
PUE: 1.24
Utility Provider: Cuerva

Alto Infrastructure is building a campus for AI data centers in the CITAI technology park in Escúzar, near Granada, and construction began in June 2026. The campus is planned in phases of modular, high-density data halls with liquid cooling, and energy group Cuerva is a partner in the project. The potential investment exceeds €3 billion, of which about €700 million covers the data center infrastructure.

Site History

  • June 2026: groundbreaking and start of construction.
  • December 2025: the project was presented under the Sierra DC name.

Map and Nearby Locations

Parque Metropolitano Avenida de Íncar ( 18130 Escúzar )
Alto Infrastructure Sites
Nearby Facilities

Alto: Granada SP01 Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Alto: Granada SP01 Data Center Photos See all

Rendering of Sierra DC's Citai Campus in Granada, Spain
Source: Sierra DC

Operating Company

Operated by:

Alto Infrastructure designs, builds and operates next-generation data centers for the world’s most demanding workloads such as AI and HPC.

0
Facilities
0
Markets

News See all

Read Spain Approves Data Center Decree Requiring 80 Percent Renewable Power
Spain's Council of Ministers approved a royal decree on Nov. 20 that ties large data centers' grid access to renewable energy use. [Royal Decree 1032/2026](https://www.boe.es/diario_boe/txt.php?id=...

Spain Approves Data Center Decree Requiring 80 Percent Renewable Power

November 23, 2026 Spain

Spain's Council of Ministers approved a royal decree on Nov. 20 that ties large data centers' grid access to renewable energy use. Royal Decree 1032/2026 was published in the Official State Gazette on Nov. 21 and entered into force on Nov. 22. The approval follows Baxtel's October...

Read more
Read Merlin Pauses Two Bilbao Data Center Buildings, Cuts MEGA Plan to 704MW
[Merlin Properties](https://baxtel.com/data-centers/merlin-properties) has paused work on two buildings at its [Bilbao-Arasur data center campus](https://baxtel.com/data-center/merlin-bilbao-arasur...

Merlin Pauses Two Bilbao Data Center Buildings, Cuts MEGA Plan to 704MW

November 19, 2026 Merlin Properties

Merlin Properties has paused work on two buildings at its Bilbao-Arasur data center campus after failing to secure an electricity supply for them. The suspension covers Arasur 4 and Arasur 5 in Álava, in Spain's Basque Country. Chief executive Ismael Clemente confirmed the halt at...

Read more
Read Spain Raises Data Center Threshold to 10MW in Revised Renewables Decree
[Spain](https://baxtel.com/regions/spain) has raised the threshold at which its draft data center rules apply to 10MW from 1MW. The Ministry for Ecological Transition and the Demographic Challenge ...

Spain Raises Data Center Threshold to 10MW in Revised Renewables Decree

October 27, 2026 Spain

Spain has raised the threshold at which its draft data center rules apply to 10MW from 1MW. The Ministry for Ecological Transition and the Demographic Challenge sent the revised decree to the Council of State on October 26, Reuters reported. The text replaces an August draft that covered...

Read more
Read Spain Proposes Rules Requiring Data Centers To Source 80% Of Power From New Renewables
Spain is preparing legislation that would require data centers of 1MW or more to source at least 80% of their electricity from new renewable generation on an hourly basis. The draft rules, approved...

Spain Proposes Rules Requiring Data Centers To Source 80% Of Power From New Renewables

August 26, 2026 Spain

Spain is preparing legislation that would require data centers of 1MW or more to source at least 80% of their electricity from new renewable generation on an hourly basis. The draft rules, approved for fast-track legislation, would apply only to new data centers and undergo public consultation...

Read more
Read Solaria Launches European Data Center Platform
Solaria Launches European Data Center Platform

Solaria Launches European Data Center Platform

November 25, 2025 Spain

Spanish energy firm Solaria Energia has formally launched its European sustainable data center platform. The platform includes approximately 3.4GW of secured grid power across 400 hectares (990 acres) spanning Spain, Italy, Germany, and the UK. In addition, the company has reportedly requested...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts

Documents See all

Get Quotes
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.