Spain's Council of Ministers approved a royal decree on Nov. 20 that ties large data centers' grid access to renewable energy use. [Royal Decree 1032/2026](https://www.boe.es/diario_boe/txt.php?id=...

Spain Approves Data Center Decree Requiring 80 Percent Renewable Power

Abdul-Rahman Oladimeji

Abdul-Rahman Oladimeji

November 23, 2026

Spain's Council of Ministers approved a royal decree on Nov. 20 that ties large data centers' grid access to renewable energy use. Royal Decree 1032/2026 was published in the Official State Gazette on Nov. 21 and entered into force on Nov. 22. The approval follows Baxtel's October report on the revised draft, which raised the threshold for the main requirements to 10MW from the 1MW first proposed.
Rows of server cabinets in a data center
The decree applies to data centers whose grid access capacity is 10 megawatts or more. Covered facilities must show that at least 80 percent of their total electricity consumption comes from self-consumption or long-term power purchase agreements tied to new renewable generation and storage located in Spain. Compliance is measured through an hourly match between consumption and generation.

The regulation also sets an additionality rule. The generation backing the 80 percent target must generally have entered service no more than 36 months before the data center starts operating, with exceptions for solar, some biomass plants and repowering projects. The 80 percent requirement was first set out in an August draft that Baxtel reported.

An optional transitional regime phases the hourly matching requirement in, starting at 60 percent and rising to 70 percent in 2029 and 80 percent in 2032, according to Data Center Dynamics.

Covered facilities must also reach a Class A rating under the European energy and water efficiency labeling schemes, with a water use target of about 0.1 liters per kilowatt-hour and adjustments for local climate. A provisional cap of 1.25 on power usage effectiveness applies to some facilities through the end of 2031.

Grid access and connection rights are now conditional on compliance. Data centers may have to cut demand or disconnect during periods of grid congestion or system stress, and non-compliance can suspend access rights for up to three years. Projects already in the permitting process get six months to adapt, or three months if they are awaiting a grid access tender, and may give up their permits without losing financial guarantees.

Spain has granted 15GW of grid access capacity to data centers, 6GW on the transmission network and 9GW on distribution, with a further 20GW awaiting connection, Euronews reported.

"In the absence of this Royal Decree, we would see an impact of 5,000 million euros on our bills," said Third Vice President and Minister for Ecological Transition Sara Aagesen. The government estimates that without the rules, data center growth would add €5 billion a year to electricity costs and raise industrial bills by 25 percent.

Alongside the decree, the Council of Ministers approved an updated electricity transmission plan through 2030. The plan commits €17.14 billion to the grid, allocates capacity for 47.4GW of new demand including 9.3GW for data centers, and adds about 6,707 kilometers of transmission lines and 193 substations, pv magazine reported.

Spain DC, the national association of data center developers, says it will appeal the decree to the Supreme Court and seek a precautionary suspension, arguing the requirements are impossible to meet and amount to a de facto veto on new projects, Inspenet reported. The association has said the rules put €9 billion of investment at risk. The People's Party, which opposes the decree, has said it would repeal the regulation if it takes power.

Baxtel tracks 234 data center facilities in Spain, operated by 95 providers. The largest is Amazon's Villanueva VDG-A site at 49.8 MW.