Amazon is building a new data center campus in Spotsylvania, Virginia. On October 10, 2023, the Board of Supervisors approved a rezoning to allow for the development of a 1.9 million square ft. data center campus on approximately 329 acres. In 2023, Amazon Data Services, Inc. filed to rezone 329 acres at 4049 Massaponax Church Road & 9300 Cosner Drive from the Mixed Use-3 and -4 (MU-3 and MU-4) zoning districts to Industrial-2 (I-2) to develop a data center campus.
The land is currently undeveloped and mostly woodland. The company aims to develop approximately 1.9 million square feet of data center space and two substations.
Phase one would see two 250,000 sq ft data centers and a substation built alongside an office building, water treatment facility, and logistics facility. It's unclear how many buildings the campus would hold at full build-out.
Buildings
| Site | Operator | Status | Operational | Building Size | Built |
|---|---|---|---|---|---|
| Global PlazaInterested in this information?Contact us | Amazon AWS |
Operational
|
░░░░ Request Dataset MW | ░░░░░░░ Request Dataset SqFt | 2025 |
| South HubInterested in this information?Contact us | Amazon AWS |
Operational
|
░░░░ Request Dataset MW | ░░░░░░░ Request Dataset SqFt | 2026 |
| Campus PlusInterested in this information?Contact us | Amazon AWS |
Under Construction
|
— | — | 2027 |
| Point ThreeInterested in this information?Contact us | Amazon AWS |
Under Construction
|
— | — | 2027 |
| CloudInterested in this information?Contact us | Amazon AWS |
Under Construction
|
— | — | 2028 |
| Prime ParkInterested in this information?Contact us | Amazon AWS |
Planned
|
— | — | 2028 |
| Metro ValleyInterested in this information?Contact us | Amazon AWS |
Planned
|
— | — | 2029 |