North Carolina regulators approved a new rate schedule for large data centers on Nov. 16, with the new terms taking effect Jan. 1. The orders from the North Carolina Utilities Commission require facilities above 100MW to sign contracts of at least 15 years and to pay for at least 75% of their contracted demand whether or not they use it, Duke Energy said. The schedule covers data centers that draw 50MW or more.
Duke Energy Carolinas and Duke Energy Progress sell power to the data centers under the schedule. The commission approved the new terms alongside two-year rate plans
Featured: Wide exterior photograph of the Duke Energy Plaza headquarters tower in Uptown Charlotte, North Carolina.for both utilities. WRAL reports the plans are projected to raise residential rates about 9.5% for Duke Energy Carolinas customers and 9.3% for Duke Energy Progress customers over two years.
A data center operator pays up front, through a contribution in aid of construction, for facilities built only to serve its site. The operator must also post a letter of credit covering transmission network upgrades and faces liquidated damages for early termination. A stranded-generation charge requires security and an extra payment at the end of the contract if the customer leaves early, under a method the commission has not set yet. The schedule also adds interim curtailment, which lets Duke reduce a data center's demand during capacity shortages or grid stress.
The settlements cut Duke's original requests. Duke Energy Carolinas will collect about $496 million over two years, down from $1,002 million, and Duke Energy Progress about $338 million, down from $729 million, according to MLQ. The commission authorized a 9.8% return on equity for both utilities, below the 10.95% Duke requested. A typical residential customer using 1,000 kilowatt-hours a month would pay $6.53 more from January 2027 under Duke Energy Carolinas and $9.62 more under Duke Energy Progress.
The commission acted on a load surge. Between March 2024 and April 2026, Duke signed contracts to supply 6.7GW of capacity to new large customers in the Carolinas, and data centers account for 92% of that contracted demand, the commission found.
"We listened to our customers and worked closely with stakeholders to find a more cost-effective way forward," said Kendal Bowman, Duke Energy's North Carolina president. "This outcome keeps affordability at the forefront while allowing us to make the investments needed to strengthen reliability and support North Carolina's continued growth."
North Carolina Attorney General Jeff Jackson asked the commission in September to create a separate rate class for data centers, NC Newsline reported. The commission set contract terms for large data centers rather than a new customer class, according to MLQ.
Baxtel tracks 129 data centers in North Carolina, operated by 63 providers. The largest is Google's Lenoir 3 site at 115MW. Duke must submit revised revenue calculations within 10 days of the orders and updated rate schedules for approval within 30 days. The two utilities combine into a single company on Jan. 1, 2027.