Global commissioned colocation capacity reached 77.6GW in the third quarter, according to DatacenterHawk. The figure, from the firm's 3Q 2026 Global Data Center Market Report, covers capacity that is built or preleased. That total exceed
Featured: Exterior view of a SoftBank AI data center campus representing the parent developer executing the record 8GW Ohio lease.s the 51GW DatacenterHawk recorded for all of 2025. Global colocation vacancy fell to 1.8 percent from 3.5 percent.
Leasing set a record in the quarter. DatacenterHawk counted 18GW leased worldwide, with North America taking 13.5GW, or 73 percent of it. APAC followed at 3.4GW, Europe at 1.1GW, the Middle East at 232MW and Latin America at 11MW. North America's vacancy rate, 0.87 percent, is the lowest of any region in the report, and Latin America's 6.46 percent is the highest.
A single lease accounts for most of the North American total. DatacenterHawk's North American report credits one 8GW deal in Ohio with more than half of the region's third-quarter leasing. That matches the 20-year lease OpenAI signed with SB Energy for roughly 8GW of IT capacity at the PORTS-Pike Technology Campus near Piketon, Ohio.
SB Energy, a SoftBank Group company, develops, owns and operates the campus. OpenAI leases the capacity, and NVIDIA is the exclusive compute supplier and has invested $1.5 billion in SB Energy, per Data Center Frontier. The first 800MW at PORTS-Pike is due in 2028, and the buildout runs through 2032. Baxtel reported the deal in August. The transmission serving the campus, about 50 miles of new 765kV line, is part of AEP Ohio's Piketon Area Improvements Project. The plan still requires approval from the Ohio Power Siting Board.
Portsmouth, Ohio, tops DatacenterHawk's 2026 absorption ranking at 8,024MW, a new entrant to the list. Austin ranks second at 3,234MW, up from 23rd in 2025. Dallas-Fort Worth follows at 2,532MW, then West Texas at 1,897MW and Melbourne at 1,546MW. Three of the five leading markets sit in Texas, and twenty-one markets leased 100MW or more in the quarter, three times as many as a year earlier. "These deals are getting bigger. A lot of GPU-as-a-service business is driving this," said Ed Socia, regional director for North America at DatacenterHawk.
In Europe, the Nordics reached 49 percent of the year's leasing. The Frankfurt, London, Amsterdam, Paris and Dublin markets fell to 23 percent, DCD reported. APAC leased more in the third quarter than in all of 2025 as neoclouds paid a premium for faster delivery. DCD places the leading market in Portsmouth, New Hampshire, while DatacenterHawk's North American report puts it in Ohio.
Baxtel tracks 6,122 data center facilities in the United States, operated by 985 providers, with Lancium's Abilene campus in Texas the largest at 1,200MW.