The University of Cambridge built the West Cambridge Data Centre as the central facility for its data strategy, serving three main users: the High Performance Computing Service, University Information Services and Cambridge Assessment. The £20 million building has four data halls plus supporting technical and office space. At handover the HPC hall was designed for up to 900 kW across 96 cabinets, with 201 kW for Cambridge Assessment, 240 kW for University Information Services, and the fourth hall left empty for future growth. The site takes two 11 kV feeds and has N+1 standby generators rated at 1,760 kW and N+1 UPS rated at 1,620 kW. Cooling combines back-of-rack units with CRAH systems. The data centre now houses the Dawn AI supercomputer.
Site History
- March 2015: The University officially opened the data centre.
- July 2014: The building was handed over to the University.