STACKIT: Ostermiething DC10

Year Built: 2018
PUE: 1.2
░░░ Request Dataset MW
Total Power
░░░░░░ Login to view SqFt
Gross Colocation Size

DC10, with its first phase completed in 2018, provides up to 1,000 sqm of data hall space. A planned second phase will add another 4,500 sqm. The facility reports a PUE of 1.1 and uses river cooling.

Power


  • Two separate power lines, connected with three power grids
  • In-house transformer stations
  • Redundant low-voltage main distribution boards
  • Module-based, power supply units to avoid interruptions (double design)
  • Spare power supply unit with fuel storage and delivery contracts for 72 hours
  • PUE < 1,2

Map and Nearby Locations

Weilhartstraße 92
STACKIT Sites
Nearby Facilities

STACKIT: Ostermiething DC10 Power Growth Over Time

+0% since 2022
Operational
Construction
Planned
Prospective
In Doubt
Withdrawn
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

STACKIT: Ostermiething DC10 Data Center Photos See all

Operating Company

Operated by:

The cloud provider STACKIT is part of Schwarz Group. External partners and customers in the DACH region can also rely on the cloud services that Schwarz Group companies have been benefiting from for years for their digital transformation. With digital sovereignty that goes far beyond the market standard and individual approaches to the implementation and operation of cloud solutions, STACKIT provides holistic support for digitalization projects. Based in Neckarsulm, Germany, the team is paving the way for an independent Europe – digital, leading. As part of Schwarz Digits, STACKIT GmbH & Co. KG is part of the IT and digital division of Schwarz Group.

4
Facilities
3
Markets
3MW
Megawatts

News See all

Read Cellnex completes €800m Austrian tower exit
Cellnex completes €800m Austrian tower exit

Cellnex completes €800m Austrian tower exit

January 01, 2025 Austria

Cellnex has completed the sale of its Austrian unit to a consortium comprised of Vauban Infrastructure Partners, EDF Invest, and MEAG for €803 million ($834m), bringing an end to Cellnex's presence in Austria after it entered the market in 2021, when it snapped up CK Hutchison's sites in the...

Read more
Read University of Innsbruck integrates quantum computer with HPC cluster
University of Innsbruck integrates quantum computer with HPC cluster

University of Innsbruck integrates quantum computer with HPC cluster

July 25, 2024 Austria

The University of Innsbruck, Austria has integrated a quantum computer into a high-performance computing (HPC) environment for the first time in Austria. The Innsbruck team has connected the university’s LEO5 cluster with AQT's IBEX Q1 quantum computer. “With the advent of quantum computers and...

Read more
Read More News

Podcasts See all

See More Podcasts

Documents See all

Ready to Level up Your
Data Center Strategy?