Under the codename Project Fighting Pike, Critical Data House (CDH) is developing a new 300-acre campus in Williams County. The development includes seven buildings, ranging from 275,000 to 500,000 sq ft (25,550 to 46,450 sqm). These facilities will utilize a closed-loop cooling system with direct-to-chip liquid cooling.
- Update: Data center master plan submitted to City of Williston was approved on March 17 th , 2025.
Construction is slated for Q2 2025 to Q4 2027, with the first phase involving two buildings. The full three-phase build-out is anticipated to take ten years, representing a potential investment of $5 billion by CDH, with an additional $5 billion for IT hardware.
- Two (2) pre-cast concrete partners standing by to begin work casting concrete tilt up walls. 300 laborers dedicated to this scope of work.
- Three (3) fiber carriers available to provide dark and lit fiber to Denver, Chicago, MSP, Lincoln and Omaha and Seattle.
- Pioneer power generation plant-600 megawatts-operating today.
- 300-megawatt power will serve letter in hand with an option to grow to 600 megawatts.