Jupiter B1 is building 1 of 4 at Project Jupiter, a hyperscale AI data center campus in Santa Teresa, Doña Ana County, New Mexico, on the New Mexico side of the El Paso metro, along NM-136 (Pete V. Domenici Highway) leading to the Santa Teresa Port of Entry. It is one of the flagship sites in OpenAI's roughly $500 billion Stargate program.
BorderPlex Digital Assets (Austin) assembled the land, and STACK Infrastructure (Colorado) is developing the buildings. Oracle (Oracle Cloud Infrastructure) is the tenant and operator on an 18-year lease, OpenAI is the primary client, and Doña Ana County hosts the project.
Construction began in September 2025, and by October 2026 more than 5,000 workers were on site. The first building topped out in October 2026. The project first targeted initial operations in late 2026. Permitting delays for the on-site fuel-cell power plant and its gas supply pipeline pushed that back, and Oracle says the campus remains on its 2028 delivery schedule.
The project is contested. A nonprofit and two residents sued the county over the $165 billion industrial-revenue-bond and tax-rebate approval. The county issued breach notices under the bond agreement in October 2026, over the power plan, and in November 2026, over late jobs reports. The New Mexico State Land Office denied the Green Chile gas pipeline's right-of-way, though the BLM later approved a federal-land route.
Project Profile
- Buildings: four data center buildings and a warehouse
- Investment: $50 billion over the first five years, up to $165 billion over 30 years
- Cooling: closed-loop, low-water design (about 20,000 gallons/day average)
- Jobs: roughly 2,500 construction, 750 permanent