Data Center Campus
Project Jupiter is a hyperscale AI data center campus in Santa Teresa, Doña Ana County, New Mexico, on the New Mexico side of the El Paso metro, along NM-136 (Pete V. Domenici Highway) leading to the Santa Teresa Port of Entry. It is one of the flagship sites in OpenAI's roughly $500 billion Stargate program.
Construction began in September 2025 along the state highway to the Santa Teresa Port of Entry, targeting initial operations in Q4 2026; by spring 2026 the site had 1,200-plus workers and 1,600-plus daily onsite personnel. The project is contested: a nonprofit and two residents sued the county over the $165 billion industrial-revenue-bond and tax-rebate approval, and the New Mexico State Land Office denied the Green Chile gas pipeline's right-of-way, though the BLM later approved a federal-land route. In July 2026 Oracle released revised energy plans projected to cut NOx emissions about 92%.
Buildings
| Site | Operator | Status | Operational | Building Size | Built |
|---|---|---|---|---|---|
| Cloud HubInterested in this information?Contact us | OpenAI |
Under Construction
|
— | — | 2026 |
| CoreInterested in this information?Contact us | OpenAI |
Under Construction
|
— | — | 2027 |
| South StationInterested in this information?Contact us | OpenAI |
Planned
|
— | — | 2028 |
| PlusInterested in this information?Contact us | OpenAI |
Planned
|
— | — | 2028 |
| TowerInterested in this information?Contact us | OpenAI |
Prospective Expansion
|
— | — | — |