Central StationInterested in this information?Contact us

Latest Podcast Street AddressInterested in this information?Contact us, Piketon, OH 45661, United States
Under ConstructionLand BankPlanned
Multi-phase development project with construction underway
Operated by:

OpenAI: PORTS Tech Campus

Site planned for 2028 and has expansions through 2030
PUE: 1.04
Utility Provider: AEP Ohio
This site is leased from SB Energy in the SB Energy: PORTS Tech Campus building

The data center project at the PORTS Technology Campus in Piketon, Ohio, is a massive computing development being custom-built by SB Energy, a SoftBank Group company, in partnership with the U.S. Department of Energy (DOE).

Located on a 3,700-acre decommissioned uranium enrichment site, the facility is designed for an unprecedented total capacity, with OpenAI slate to become the primary operational anchor tenant. Under a long-term lease, OpenAI will use the campus to train and deploy its next-generation artificial intelligence models. To support this massive computational load without impacting the local grid, SB Energy is spearheading the development of independent on-site natural gas generation, paired with additional power infrastructure.

Groundbreaking for the site occurred in March 2026, starting with an initial $10 billion phase. This first phase consists of four to six high-density buildings packed with Nvidia hardware and engineered using National Laboratory of the Rockies (NLR) liquid cooling specifications, which aim for a highly efficient 1.036 PUE. While physical construction of the first buildings is scheduled for completion in early 2028, full power activation through AEP Ohio transmission upgrades is projected for 2029.

Map and Nearby Locations

This Facility
OpenAI Sites
Nearby Facilities

Campus PrimeInterested in this information?Contact us Power Growth Over Time

Operational
Construction
Planned
Prospective
In Doubt
Withdrawn
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of BetaInterested in this information?Contact us

Distance Site About
NN milesInterested in this information?Contact us SB Energy: PORTS Tech Campus
The data center project at the PORTS Technology Campus in Piketon, Ohio, is a development overseen by SB Energy, a SoftBank Group company, in partnership with the U.S. Department of Energy (DOE).

Operating Company

Operated by:
0
Facilities
0
Markets

News See all

Read Veolia to Operate 350MW Gas-Fired Microgrid for Ohio Data Center Campus
French energy and water utility Veolia has been selected to operate and maintain a 350MW microgrid powering an undisclosed AI data center campus in Ohio. The behind-the-meter energy system is desig...

Veolia to Operate 350MW Gas-Fired Microgrid for Ohio Data Center Campus

July 31, 2026 Ohio

French energy and water utility Veolia has been selected to operate and maintain a 350MW microgrid powering an undisclosed AI data center campus in Ohio. The behind-the-meter energy system is designed to supply 100% of the facility’s power needs, combining gas engines, linear generators, and a...

Read more
Read Real Estate Firm Explores Potential Data Center Project in Amherst, Ohio
Cervenka Development Partners is exploring a potential data center project in Amherst, Ohio. The company has applied for a zoning variance to allow data center use on industrial land parcels along ...

Real Estate Firm Explores Potential Data Center Project in Amherst, Ohio

July 22, 2026 Ohio

Cervenka Development Partners is exploring a potential data center project in Amherst, Ohio. The company has applied for a zoning variance to allow data center use on industrial land parcels along Nordson Drive. The request will be reviewed by the City of Amherst Zoning Board of Appeals on July...

Read more
Read OpenAI in Early Talks for 10GW Data Center Lease in Ohio
OpenAI is in advanced talks to lease a proposed 10GW data center in Ohio being developed by SB Energy on US Department of Energy land at the Portsmouth Site in Pike County. The project, backed by S...

OpenAI in Early Talks for 10GW Data Center Lease in Ohio

June 10, 2026 OpenAI

OpenAI is in advanced talks to lease a proposed 10GW data center in Ohio being developed by SB Energy on US Department of Energy land at the Portsmouth Site in Pike County. The project, backed by SoftBank Group, could be built in phases starting with an 800MW first stage expected in 2028, with...

Read more
Read $1.6bn Cleveland Data Center Plan Rejected
$1.6bn Cleveland Data Center Plan Rejected

$1.6bn Cleveland Data Center Plan Rejected

May 18, 2026 Ohio

Cleveland, Ohio, has turned down Lakeland Equity Group’s $1.6 billion plan to develop a data center campus. Mayor Justin M. Bibb announced on May 14 that the city had denied the permit for the proposed facility, which was planned for a 35-acre site at 3560 E 55th St. Lakeland described the...

Read more
Read Developers Submit Plans for $1.6 Billion Data Center in Cleveland, Ohio
Developers Submit Plans for $1.6 Billion Data Center in Cleveland, Ohio

Developers Submit Plans for $1.6 Billion Data Center in Cleveland, Ohio

May 08, 2026 Ohio

Private credit firm Lakeland Equity Group has filed plans for a $1.6 billion data center project in Cleveland, Ohio. The proposal outlines a 150MW campus on a 35-acre site at 3560 E 55th St, currently owned by trucking company Morabito Enterprises. The development could include three two-story...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse