In April 2025, Microsoft put its data center construction plans on hold in New Albany, Heath, and Hebron. Prior to this, in 2023, Microsoft acquired 183 acres from MBJ Holdings LLC, a New Albany Co. affiliate, for $56.9 million ($310,000 per acre). This property, located between Beech Road and the Licking-Franklin county line, currently consists mostly of farmland with two single-family homes.
Previously, the tech giant had planned to build a 245,000-square-foot data center employing 30 people directly, with additional indirect jobs expected. Construction was scheduled to begin in July 2025, with completion targeted for late 2027. MBJ Holdings had purchased the land for $13.4 million in January of that year.
In October 2026, Microsoft reported that early construction works at the site were complete, with future development phases planned. AEP Ohio has filed for a new 138 kV substation on part of the property, scheduled for service in November 2027.