DC Mevspace 1 is a modular container data center that Mevspace built to Tier III standards in Wyszków, about 40 km northeast of Warsaw. It houses the company's dedicated and virtual servers and its colocation customers. Mevspace added a second service building on the plot in 2023 and signed a medium-voltage grid connection agreement in 2024 for further growth.

Site History

  • June 2024: Mevspace signed a grid connection agreement with the distribution operator.
  • September 2023: The county permitted a second service building.
  • August 2021: The county permitted the server building.
  • May 2020: The data center first appeared on PeeringDB.

Map and Nearby Locations

Serwerowa 10
Mevspace Sites
Nearby Facilities

Mevspace: DC-1 Wyszków Power Growth Over Time

+0% since 2022
Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Operating Company

Operated by:

MEVSPACE Sp. z o.o. was registered in 2010 and is based on Locciego Street in Warsaw. It sells dedicated servers, virtual servers and colocation, and runs its equipment in DC Mevspace 1, a modular container data center in Wyszków built to Tier III standards. Two individuals own the company.

0
Facilities
0
Markets

News See all

Read Korbank's Data Center Development in Warsaw Delayed Due To Specification Change
Baxtel

Korbank's Data Center Development in Warsaw Delayed Due To Specification Change

March 18, 2022 Warsaw

Polish telecommunications company, Korbank has revealed that it won’t be completing the construction of its Wroclaw data center till later. The data center was scheduled to be completed this month, but the date has been shifted to June of this year. The delay is happening because Korbank wants to...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Quotes
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.