Marathon Digital: Abu Dhabi 2

Latest Podcast Location withheld
Operational
Fully operational facility
Operated by:

Marathon Digital: Abu Dhabi 2

Year Built: 2024
░░░░ Request Dataset MW
Total Power

Marathon Digital Holdings and Zero Two, an emerging blockchain and digital assets infrastructure development company, established two large-scale Immersion Bitcoin Mining Facilities in Abu Dhabi. This facility is one of those.

Map and Nearby Locations

Location withheld
MARA Holdings Sites
Nearby Facilities

Marathon Digital: Abu Dhabi 2 Power Growth Over Time

+0% since 2022
Operational
Construction
Planned
Prospective
In Doubt
Withdrawn
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Marathon Digital: Abu Dhabi 2

Distance Site About
4.48 miles VivoPower: Abu Dhabi, UAE
VivoPower International signed an agreement to acquire, develop, and operate a data center facility in the United Arab Emirates in January 2026 from an undisclosed seller.
14.03 miles Khazna: AUH 3.1
Khazna's AUH 3.1 data center is located in the Khalifa Industrial Zone (KIZAD) in Abu Dhabi, United Arab Emirates.
14.07 miles Khazna: Abu Dhabi AUH3
Khazna AUH3 is a hyperscale-ready data center located in the Khalifa Industrial Zone (KIZAD) in Abu Dhabi, United Arab Emirates.
14.39 miles Pure DC: Yas Island 1
Pure Data Centres Group operates AUH01 Building 1, a live hyperscale data center facility on Yas Island in Abu Dhabi, United Arab Emirates.
14.75 miles Pure DC: Yas Island 2
Pure Data Centres Group is developing AUH01 Building 2 on Yas Island in Abu Dhabi as the next expansion phase of its hyperscale AUH01 campus.
16.23 miles G42: UAE-US AI Campus
US President Donald Trump and UAE President Sheikh Mohamed bin Zayed al-Nahyan have unveiled plans for a 10-square-mile AI data center campus in Abu Dhabi.
16.23 miles Hyperscale Data Center Request Dataset
G42, OpenAI, Oracle, NVIDIA, SoftBank Group, and Cisco are partnering to build Stargate UAE, a next-generation AI infrastructure cluster in Abu Dhabi.
16.29 miles Marathon Digital: Abu Dhabi 1
Marathon Digital Holdings and Zero Two, an emerging blockchain and digital assets infrastructure development company, established two large-scale Immersion Bitcoin Mining Facilities in Abu Dhabi.
16.90 miles Equinix Abu Dhabi AD1
16.92 miles Khazna: Abu Dhabi AUH1
Khazna AUH1 is a data center located in Masdar City, Abu Dhabi.
16.93 miles Khazna: Abu Dhabi AUH6
Khazna Data Centers has launched a new data center AUH6 in Masdar City, Abu Dhabi, United Arab Emirates (UAE).
16.98 miles Khazna: Masdar AUH8
Khazna is constructing a new data center in the Masdar City of UAE. The site is expected to be completed in August 2026.

Marathon Digital: Abu Dhabi 2 Data Center Photos See all

Operating Company

Operated by:

Overview

MARA Holdings (NASDAQ: MARA), formerly Marathon Digital Holdings, is one of the largest publicly traded Bitcoin miners in North America and the holder of one of the largest corporate BTC treasuries. Founded in 2013 and headquartered in Fort Lauderdale, Florida, the company is led by CEO Fred Thiel. Operations span large-scale mining campuses in West Texas (Garden City, Granbury, Permian Basin), Kearney NE, Paraguay (Hernandarias), and Abu Dhabi.

Strategic pivot to digital energy (2026)

On the Q1 2026 earnings call (reported May 11, 2026), Thiel reframed MARA as a "digital energy" company rather than a Bitcoin miner, describing the quarter as "a redefining quarter, not an incremental one." Management's stated identity going forward: "MARA deploys digital energy technologies to advance the world's energy systems and transforms excess energy into digital capital."

The pivot is being executed across three vectors:

  • AI/HPC compute. Closed acquisition of Exaion, a French AI/HPC operator spun out of EDF, giving MARA a sovereign-grade European compute footprint and customer relationships.
  • Owned power generation. Announced a $1.5 billion acquisition of Long Ridge Energy Terminal in Hannibal, Ohio, comprising a 505 MW combined-cycle natural gas plant and ~1,600 acres of adjacent land zoned for AI/HPC and digital infrastructure development.
  • Capital reallocation. Sold approximately 15,100 BTC for $1.1 billion to fund the pivot, and took $45.9 million in restructuring charges including a $41.8 million write-down on mining rigs being phased out.

Q1 2026 financials

  • Revenue: $174.6 million, down 18% year over year, with substantially all revenue still from Bitcoin mining.
  • Net loss: $1.26 billion, reflecting BTC mark-to-market and restructuring charges.
  • Strategy: maintain mining cash flow short-term while preserving optionality to convert capacity to AI/HPC.

Capex direction

New capital is flowing to AI/HPC infrastructure and owned power generation (Exaion, Long Ridge), not to new mining hashrate. Mining continues at existing campuses as a near-term cash generator and as a flexible load that can be displaced by higher-value compute as AI tenant demand materializes.

10
Facilities
6
Markets
951MW
Megawatts

News See all

Read Zero Two Invests in APAC Data Center Firm Evolution
Zero Two Invests in APAC Data Center Firm Evolution

Zero Two Invests in APAC Data Center Firm Evolution

August 13, 2025 Abu Dhabi

Zero Two has invested in Evolution, taking a co-controlling position alongside Warburg Pincus. Terms of the deal were not shared, though reports from Mingtiandi puts the figure at $325 million.Darren Webb, CEO and co-founder of Evolution Data Centres, said: “We are absolutely delighted to welcome...

Read more
Read ADNOC partners with e& for private 5G wireless networks
ADNOC partners with e& for private 5G wireless networks

ADNOC partners with e& for private 5G wireless networks

July 06, 2024 Abu Dhabi

The Abu Dhabi National Oil Company (ADNOC) has paired with telco e& to build a private 5G wireless network that spans 11,000 square kilometers which will be the largest private 5G wireless network ever built in the energy industry.“This landmark project with e& is a milestone step in...

Read more
Read Mira Aerospace successfully completes 5G trial from the stratosphere
Mira Aerospace successfully completes 5G trial from the stratosphere

Mira Aerospace successfully completes 5G trial from the stratosphere

October 31, 2023 Abu Dhabi

High altitude pseudo satellite (HAPS) firm Mira Aerospace has successfully conducted a 5G connectivity trial from the stratosphere - which ranges from 4-12 miles (6-20 km) above the Earth's surface to around 31 miles (50km). Mira said in an announcement last week, “Our team is excited to announce...

Read more
Read Mubadala of Abu Dhabi, together with KKR, invested in CoolIT
Mubadala of Abu Dhabi, together with KKR, invested in CoolIT

Mubadala of Abu Dhabi, together with KKR, invested in CoolIT

July 06, 2023 Abu Dhabi

The Mubadala Investment Company of Abu Dhabi disclosed earlier this year that it had invested in liquid cooling company CoolIT. In May 2023, the company invested alongside KKR in the Canadian company, with the latter acquiring the majority of the cooling business. The terms of the acquisition...

Read more
Read Emerge to provide Khazna Data Centers with renewable energy from solar plant development
Emerge to provide Khazna Data Centers with renewable energy from solar plant development

Emerge to provide Khazna Data Centers with renewable energy from solar plant development

October 18, 2022 Abu Dhabi

Emerge, a joint venture (JV) between Masdar and EDF, has signed an agreement with Khazna Data Centers to provide it with renewable energy from a new solar plant development. The ground-mounted solar photovoltaic (PV) plant will provide power to Khazna's new data center in Masdar City, providing...

Read more
Read More News