Hyperco, part of DAMAC's EDGNEX, plans a data center campus on about 52 hectares at Vallhalla, south of the Grönviken switching station at Lingbo in Ockelbo kommun. Ockelbo kommun's detailed plan for data centers and server halls became final in July 2026. The kommun granted building permits in October 2026 for a data center, office, switchgear buildings and a transformer station, and a site-establishment permit in November 2026. Hyperco has exclusive rights to buy the land from Kopparfors and says the site can draw hundreds of megawatts directly from Grönviken. It targets operation in November 2027, with three data halls finished in 2028, and says the build pace depends on power allocation and customer demand.
Site History
- November 2026: Ockelbo kommun granted a temporary permit for site establishment.
- October 2026: Ockelbo kommun granted building permits for the data center and a transformer station.
- July 2026: The detailed plan for the Vallhalla industrial area became final.
- June 2026: Ockelbo kommunfullmäktige adopted the detailed plan.
- May 2024: Hyperco began studying the Lingbo site.