Tonstad DataPark is building 1 of 4 on GreenScale's campus at Ertsmyra, next to Statnett's Ertsmyra transformer station in Sirdal, Agder. GreenScale bought Tonstad DataPark AS in September 2025, with 42 hectares of land ready for development. Statnett has reserved grid capacity for the campus, and NVE licensed its own 132/22 kV substation in December 2025. Site clearing began in February 2026, and GreenScale targeted the first building in 2028 and the full campus by 2030. In November 2026 the county governor overturned Sirdal's zoning decision, so the campus needs a new plan with a full impact assessment.
Site History
- November 2026: Statsforvalteren i Agder overturned Sirdal's zoning decision for the campus; a new plan with an impact assessment is required.
- February 2026: Site clearing began.
- December 2025: NVE licensed the campus substation.
- September 2025: GreenScale completed the purchase of Tonstad DataPark AS.
- June 2025: GreenScale agreed to buy the company.