Green Mountain is building SVG-Undheim as a dedicated campus for one international technology company, which has contracted the full capacity for 15 years from the handover of each stage. The two interconnected two-storey buildings sit on land zoned for power-intensive industry next to the Høg-Jæren wind farm. A new transformer station with four 132/22 kV transformers takes power through a temporary 132 kV connection until a permanent dual feed is built, which the grid licence does not expect before 2029 to 2031.
Azrieli Group, Green Mountain's owner, puts the cost at about EUR 1 billion and expects about EUR 117 million of annual net operating income at full capacity. Delivery runs in stages over about two and a half years, with the first stage now due in July 2027.
Site History
- November 2026: NVE licensed the grid connection; Statnett has confirmed capacity for the full site.
- October 2026: Azrieli signed EUR 1.4 billion of financing and moved the first stage from March to July 2027.
- June 2026: DC Nordic, a Backe and Bravida joint venture, became main contractor.
- December 2025: Azrieli announced the 15-year agreement with the customer.
- April 2025: Time municipality granted the framework permit for the two data halls.