Amazon is developing a data centre campus on the northern part of the former Didcot A coal-fired power station site, next to its existing Didcot buildings. RWE won outline planning permission for a data centre campus on the land before selling it, and Amazon has since secured reserved matters approval for four data centre buildings and a gatehouse, along with an Environment Agency permit for standby generation. This record covers the first of three three-storey halls. National Grid is extending its Didcot 400 kV substation to connect new demand in the area.
Site History
- July 2026: Environment Agency issued the standby generation permit for the campus.
- Early 2026: Vale of White Horse approved reserved matters for four data centre buildings.
- February 2026: Amended outline permission granted.
- November 2025: RWE completed the sale of the land; the buyer was reported as Amazon.
- July 2025: Outline permission granted for a data centre campus on the former power station land.
- August 2022: RWE submitted the outline planning application.