Strategically located with secured access to power and robust connectivity, the TOR01 Campus is just seven miles away from 151 Front Street, Toronto's largest carrier hotel and primary internet exchange point. Stack Infrastructure's TOR01A offers committed power, providing a secure foundation for mission-critical infrastructure.
# # Availability of Power Phasing
- Toronto-based developer First Gulf partnered with STACK to deliver the initial 8MW data center by renovating an existing building TOR01A.
- The 24MW phase of development, TOR01B, with planned delivery in the second quarter of 2026, features committed power from Toronto Hydro from three diverse substations using 100% renewable energy sources.
- The third phase, TOR01C, will offer a further 24MW, which STACK says will support client growth on a campus tailored as a purpose-built solution for scalability.