Data Center Campus
Google's first building on the campus was started in 2011 and finished in 2013 at a cost of $120 million.
A second facility was opened in 2015. The total cost of the first two facilities was estimated to be $500 million.
In August 2018, Google announced it will build a third facility for an estimated $350 million. The third building will be completed in 2020.
Buildings
| Site | Operator | Status | Operational | Building Size | Built |
|---|---|---|---|---|---|
| GlobalInterested in this information?Contact us |
Operational
|
░░░░ Request Dataset MW | ░░░░░░░ Request Dataset SqFt | 2013 | |
| Global CampusInterested in this information?Contact us |
Operational
|
░░░░ Request Dataset MW | ░░░░░░░ Request Dataset SqFt | 2017 | |
| Cloud ValleyInterested in this information?Contact us |
Operational
|
░░░░ Request Dataset MW | ░░░░░░░ Request Dataset SqFt | 2020 |