Data Center Campus
In December 2024, Corscale Data Centers secured planning approval for its first UK project, the Corscale Court Lane Data Center in Iver, Buckinghamshire. Located on a 14-acre heavy industrial estate between Slough and Hayes, the hyperscale campus will consist of two multi-story buildings and a dedicated substation.
Designed by Gensler, the scheme features sympathetic cladding to protect and architecturally blend with Iver Court Farmhouse, a Grade II-listed building on the site. Pre-development groundworks and utility rerouting are scheduled to begin in July 2026 under contractors McLaren Construction and Phoenix ME, with practical completion targeted for Q4 2029.
Buildings
| Site | Operator | Status | Operational | Building Size | Built |
|---|---|---|---|---|---|
| CorScale: Court Lane 1 | Corscale |
Planned
|
— | — | 2028 |
| CorScale: Court Lane 2 | Corscale |
Planned
|
— | — | 2029 |