Data Center Campus
Amazon Web Services data center campus under construction on the west side of Beech Road in Jersey Township, Licking County, in the New Albany cluster.
Amazon Data Services bought about 392 acres along Beech and Miller roads in January 2023 for $116.7 million. Filings with the Ohio EPA that month described up to 18 data center buildings on the west side of Beech Road, known as the North Beech Corridor West.
Construction of the first buildings started in June 2025. AEP Ohio is building the Curleys 345 kV substation on 18 acres it bought from Amazon at the north end of the site.
Buildings
| Site | Operator | Status | Operational | Building Size | Built |
|---|---|---|---|---|---|
| Ridge PlusInterested in this information?Contact us | Amazon AWS |
Under Construction
|
— | — | 2027 |
| Edge PointInterested in this information?Contact us | Amazon AWS |
Under Construction
|
— | — | 2027 |
| Park UltraInterested in this information?Contact us | Amazon AWS |
Under Construction
|
— | — | 2028 |
| Cloud ValleyInterested in this information?Contact us | Amazon AWS |
Under Construction
|
— | — | 2028 |
| Prime PlazaInterested in this information?Contact us | Amazon AWS |
Under Construction
|
— | — | 2028 |
| PrimeInterested in this information?Contact us | Amazon AWS |
Planned
|
— | — | 2029 |