Kumo Networks inaugurated its second Spanish data center on 17 November, a 2.4MW facility in Paterna that began operating in June. The Paterna site at the Táctica business park has more than 1,000 sqm (10,763 sq ft) of IT rooms, according to Kumo's opening announcement.
Featured: Photograph from the official inauguration ceremony of the 2.4MW Kumo Networks facility in Paterna.
Kumo owns and operates the facility, which it uses to sell colocation, infrastructure as a service and hybrid cloud to companies and public administrations. The building also works as a neutral interconnection point, with separate halls for carriers and multiple fiber entry points. Economía Digital reports that Kumo holds a five-year power supply contract with Iberdrola and that renewable energy currently accounts for more than 80 percent of consumption.
El Corte Inglés took full ownership of the business in October 2024, buying the 50 percent of KIO Networks España it did not control, Expansión reported. The rebrand to Kumo was completed at the end of 2025. Kumo also runs the Murcia facility on the Espinardo university campus, which opened in 2014 with 172 sqm and 193kW in a single data hall, DCD reported.
The Uptime Institute certified the Paterna site at Tier IV, and Kumo says it is the only Spanish provider with two interconnected Tier IV data centers. The site also holds ENS high-category certification for its colocation and cloud services, alongside ISO 27001, 27017, 27018 and 22301.
About 30 percent of Paterna's capacity has been taken, Las Provincias reported. Kumo has not disclosed the project cost; KIO put the investment at around 50 million euros when construction started, according to the same report. The company employs 80 people, 35 of them in Paterna.
Cooling at the site relies on a geothermal field of 71 wells and a CO2-based system running on a closed water loop that needs one initial fill, operations director Manuel Moreno said at the opening. Kumo says the facility recovers waste heat from its servers and uses no water for continuous cooling.
Baxtel tracks 9 data center facilities in Valencia, operated by 9 providers. The largest is Nunsys' Paterna site at 3.5MW.
Spain's draft data center decree would apply to facilities above 10MW and require them to cover 80 percent of consumption with new renewable generation matched hour by hour, Economía Digital reported. Kumo intends to stay under that threshold. "It would affect new projects, obviously. Our business model is to go to edge data centers, to facilities close to customers," chief executive Laura Galián said at the opening, according to Las Provincias. Moreno said a market such as Madrid could hold several 6MW to 7MW facilities instead of one large campus. The government intends to approve the decree before the 29 November general election.